| Kottakkal PH Sn AE |
| Date: 11/05/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 10/04/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 26/03/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 16/03/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 12/03/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 07/03/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 02/03/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 27/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 23/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 18/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 11/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 06/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 02/02/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 29/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 17/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 12/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 09/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 08/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 03/01/2026 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 29/12/2025 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 24/12/2025 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 22/12/2025 |
Work in progress | 20% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 17/10/2025 |
Work in progress | 1% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 15/09/2025 |
Work has started | 0% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 11/09/2025 |
Work has started | 0% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 25/08/2025 |
Work has started | 0% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 20/08/2025 |
Work has started | 0% Completed
Work in progress.
| Edappal PH Dn EE |
| Date: 06/08/2025 |
Work in progress | 10% Completed
Work in progress.
| Edappal PH Dn EE |
| Date: 14/07/2025 |
Work in progress | 10% Completed
Work in progress.
| Edappal PH Dn EE |
| Date: 25/06/2025 |
Work in progress | 10% Completed
Work in progress.
| Edappal PH Dn EE |
| Date: 09/06/2025 |
Work in progress | 10% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 12/05/2025 |
Work in progress | 10% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 24/03/2025 |
Work in progress | 10% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 05/03/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 25/02/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 19/02/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 07/02/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 29/01/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 24/01/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 15/01/2025 |
Work in progress | 5% Completed
Informed panchayath regarding for the balance connection.
| Edappal PH Dn EE |
| Date: 01/01/2025 |
Work has started | 0% Completed
Pipe test arranged. work will start soon.
| Edappal PH Dn EE |
| Date: 24/12/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 17/12/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 10/12/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 05/12/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon
| Edappal PH Dn EE |
| Date: 27/11/2024 |
Work in progress | 0% Completed
Pipe test arranged.work will start soon
| Edappal PH Dn EE |
| Date: 23/11/2024 |
Work in progress | 0% Completed
Pipe test arranged.work will start soon
| Edappal PH Dn EE |
| Date: 18/11/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 11/11/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 05/11/2024 |
Work in progress | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 29/10/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.
| Edappal PH Dn EE |
| Date: 22/10/2024 |
Work has started | 0% Completed
Pipe test arranged.work will start soon.