Painavu PH Section AE
Date: 31/05/2023

Work has been completed | 100% Completed

CC Ist & Final Bill Submitted

Painavu PH Section AE
Date: 08/03/2023

Work in progress | 90% Completed

Bill under preparation

Painavu PH Section AE
Date: 27/02/2023

Work in progress | 90% Completed

Bill under preparation

Painavu PH Section AE
Date: 21/02/2023

Work in progress | 89% Completed

Line Charge Completed

Painavu PH Section AE
Date: 14/02/2023

Work in progress | 87% Completed

Line Charging Works going on

Painavu PH Section AE
Date: 06/02/2023

Work in progress | 85% Completed

Pipe Laying Completed

Painavu PH Section AE
Date: 25/01/2023

Work in progress | 80% Completed

Pipe Laying work is almost done

Painavu PH Section AE
Date: 20/01/2023

Work in progress | 75% Completed

Pipe Laying work is almost done

Painavu PH Section AE
Date: 10/01/2023

Work in progress | 68% Completed

Pipe laying work is going on

Painavu PH Section AE
Date: 04/01/2023

Work in progress | 65% Completed

Pipe laying work is going on

Painavu PH Section AE
Date: 26/12/2022

Work in progress | 62% Completed

Pipe Laying Work in Progress

Painavu PH Section AE
Date: 17/12/2022

Work in progress | 60% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 13/12/2022

Work in progress | 60% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 08/12/2022

Work in progress | 60% Completed

Work in progress

Painavu PH Section AE
Date: 03/12/2022

Work in progress | 60% Completed

Work on going

Painavu PH Section AE
Date: 29/11/2022

Work in progress | 60% Completed

Work on going

Painavu PH Section AE
Date: 24/11/2022

Work in progress | 40% Completed

work on going

Painavu PH Section AE
Date: 16/11/2022

Work in progress | 10% Completed

Pipe supply done, work started

Painavu PH Sub Dn AEE
Date: 06/11/2022

Work in progress | 4% Completed

work in progress

Painavu PH Sub Dn AEE
Date: 15/10/2022

Work has started | 0% Completed

pipe test conducted on 14.10.22

Painavu PH Section AE
Date: 03/10/2022

Work in progress | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 02/10/2022

Work has started | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 20/09/2022

Work has started | 0% Completed

Agreement executed

Painavu PH Section AE
Date: 17/09/2022

Work has started | 0% Completed

Work order issued

Painavu PH Section AE
Date: 13/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Section AE
Date: 01/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Sub Dn AEE
Date: 28/08/2022

Work has started | 0% Completed

work order issued

Thodupuzha PH Dn EE
Date: 26/08/2022

Work has started | 0% Completed

work order issued