Cheruvathur AE |
Date: 07/06/2022 |
Work has been completed | 100% Completed
work completed
Cheruvathur AE |
Date: 22/05/2022 |
Work has been completed | 100% Completed
work completed
Cheruvathur AE |
Date: 07/12/2021 |
Work has been completed | 100% Completed
completed
Cheruvathur AE |
Date: 30/11/2021 |
Work has been completed | 100% Completed
completed
Kanhangad AEE |
Date: 26/11/2021 |
Work has been completed | 100% Completed
completed
Kanhangad AEE |
Date: 23/11/2021 |
Work has been completed | 100% Completed
completed
Cheruvathur AE |
Date: 22/11/2021 |
Work has been completed | 100% Completed
completed
Kanhangad AEE |
Date: 16/11/2021 |
Work has been completed | 100% Completed
completed
Kanhangad AEE |
Date: 11/11/2021 |
Work has been completed | 100% Completed
completed
Cheruvathur AE |
Date: 07/11/2021 |
Work has been completed | 100% Completed
completed
Kanhangad AEE |
Date: 01/11/2021 |
Work in progress | 76% Completed
work temporarily stopped for want of road cutting permission from PWD
Cheruvathur AE |
Date: 30/10/2021 |
Work in progress | 76% Completed
work temporarily stopped for want of road cutting permission from PWD
Kanhangad AEE |
Date: 25/10/2021 |
Work in progress | 75% Completed
work temporarily stopped for want of road cutting permission from PWD
Cheruvathur AE |
Date: 20/10/2021 |
Work in progress | 75% Completed
work temporarily stopped for want of road cutting permission from PWD
Cheruvathur AE |
Date: 13/10/2021 |
Work in progress | 75% Completed
480 FHTC physcically given out of 480 FHTC.PWD road cutting permission awaiting for completing the work. jjm entry 362 fhtc
Cheruvathur AE |
Date: 06/10/2021 |
Work in progress | 75% Completed
480 FHTC physcically given out of 480 FHTC.PWD road cutting permission awaiting for completing the work. jjm entry 362 fhtc
Cheruvathur AE |
Date: 29/09/2021 |
Work in progress | 71% Completed
454 jjm entry effected out of 480 fhtc .
Cheruvathur AE |
Date: 22/09/2021 |
Work in progress | 71% Completed
ststus remains same
Cheruvathur AE |
Date: 13/09/2021 |
Work in progress | 70% Completed
480 fhtc physically given. jjm entry 423,waiting for pwd road cutting permission
Cheruvathur AE |
Date: 06/09/2021 |
Work in progress | 68% Completed
480 fhtc physically given. waiting for pwd road cutting permission
Cheruvathur AE |
Date: 28/08/2021 |
Work in progress | 67% Completed
480 fhtc physically given. waiting for pwd road cutting permission
Cheruvathur AE |
Date: 23/08/2021 |
Work in progress | 65% Completed
470 fhtc physically given. waiting for pwd road cutting permission
Kanhangad AEE |
Date: 18/08/2021 |
Work in progress | 61% Completed
480 fhtc completed
Cheruvathur AE |
Date: 11/08/2021 |
Work in progress | 60% Completed
470 fhtc completed .
Cheruvathur AE |
Date: 05/08/2021 |
Work in progress | 60% Completed
470 fhtc completed . 2 nd part bill submitted
Cheruvathur AE |
Date: 02/08/2021 |
Work in progress | 60% Completed
470 FHTC physically completed out of 480 FHTC
Cheruvathur AE |
Date: 29/07/2021 |
Work in progress | 58% Completed
404 fhtc completed
Cheruvathur AE |
Date: 26/07/2021 |
Work in progress | 56% Completed
360 FHTC complated 2 nd part bill submitted
Cheruvathur AE |
Date: 22/07/2021 |
Work in progress | 55% Completed
360 FHTC complated 2 nd part bill submitted
Cheruvathur AE |
Date: 15/07/2021 |
Work in progress | 50% Completed
275 fhtc given 2 nd part bill submitted
Cheruvathur AE |
Date: 12/07/2021 |
Work in progress | 50% Completed
253 FHTC partially given .
Cheruvathur AE |
Date: 07/07/2021 |
Work in progress | 48% Completed
95 fhtc completed .part bill submitted
Cheruvathur AE |
Date: 02/07/2021 |
Work in progress | 46% Completed
72 fhtc completed ,waiting for road cutting permission from PWD
Cheruvathur AE |
Date: 28/06/2021 |
Work in progress | 45% Completed
72 fhtc completed,part bill submitted
Cheruvathur AE |
Date: 15/06/2021 |
Work in progress | 42% Completed
part bill submitted ,pwd joint inspection conducted
Cheruvathur AE |
Date: 11/06/2021 |
Work in progress | 40% Completed
bill under preparation,awaiting for PWD road cutting permission
Cheruvathur AE |
Date: 01/06/2021 |
Work in progress | 25% Completed
pipe supplied,56 FHTC out of 480 FHTC completed .work progressing on
Cheruvathur AE |
Date: 18/03/2021 |
Work in progress | 1% Completed
earth work started
Cheruvathur AE |
Date: 15/03/2021 |
Work in progress | 1% Completed
Order placed for PVC pipes