| Kozhikode Dist 1 Sn 2 - AE |
| Date: 21/08/2024 |
Work has been completed | 100% Completed
Work completed
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 92% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 90% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 87% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 85% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 82% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 78% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 75% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 73% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 70% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 62% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work in progress | 60% Completed
Work Started
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 55% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work in progress | 46% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work in progress | 45% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work in progress | 35% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 08/08/2023 |
Work in progress | 30% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work in progress | 25% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work in progress | 12% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 05/07/2023 |
Work in progress | 10% Completed
Pipe laying started.
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
Tender Accepted
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 25/05/2023 |
Work has started | 0% Completed
Agreement Executed