| Kannur PH Dn EE |
| Date: 11/06/2026 |
Work in progress | 34% Completed
7 km of pipeline laid and 65 Nos of HTC given
| Kannur PH Dn EE |
| Date: 02/06/2026 |
Work in progress | 34% Completed
7 km of pipeline laid and 65 Nos of HTC given
| Kannur PH Dn EE |
| Date: 25/04/2026 |
Work in progress | 33% Completed
6.10 km of pipeline laid and HTC 23 Nos
| Kannur PH Dn EE |
| Date: 16/04/2026 |
Work in progress | 33% Completed
6.00 km of pipeline laid
| Kannur PH Dn EE |
| Date: 08/04/2026 |
Work in progress | 33% Completed
6.00 km of pipeline laid
| Kannur PH Dn EE |
| Date: 30/03/2026 |
Work in progress | 33% Completed
6.00 km of pipeline laid
| Kannur PH Dn EE |
| Date: 21/03/2026 |
Work in progress | 33% Completed
6.00 km of pipeline laid
| Kannur PH Dn EE |
| Date: 11/03/2026 |
Work in progress | 25% Completed
3.20 km of pipeline laid
| Kannur PH Dn EE |
| Date: 02/03/2026 |
Work in progress | 25% Completed
2.80 km of pipeline laid
| Kannur PH Dn EE |
| Date: 20/02/2026 |
Work in progress | 24% Completed
1.622 km of pipeline laid
| Kannur PH Dn EE |
| Date: 10/02/2026 |
Work in progress | 24% Completed
1.358 km of pipeline laid
| Kannur PH Dn EE |
| Date: 31/01/2026 |
Work in progress | 24% Completed
0.70 km of pipeline laid
| Kannur PH Dn EE |
| Date: 20/01/2026 |
Work in progress | 23% Completed
Pipe supplied, work started
| Kannur PH Dn EE |
| Date: 09/01/2026 |
Work in progress | 1% Completed
Pipe supplied
| Kannur PH Dn EE |
| Date: 29/12/2025 |
Work in progress | 1% Completed
pipe supplied