Koothuparamba Proj AE 2
Date: 26/05/2022

Work has been completed | 100% Completed

completed and commissioned.Final bill paid

Koothuparamba Proj AE 2
Date: 22/04/2022

Work has been completed | 100% Completed

Work completed on 14/03/22.Final bill submitted

Koothuparamba Proj AE 2
Date: 17/03/2022

Work has been completed | 100% Completed

work completed,Final bill submitted.

Koothuparamba Proj AE 2
Date: 14/03/2022

Work in progress | 99% Completed

Railway crossing work completed.Trial running started.

Koothuparamba Proj AE 2
Date: 10/03/2022

Work in progress | 99% Completed

Railway crossing by Push through method in progress.

Koothuparamba Proj AE 2
Date: 06/03/2022

Work in progress | 98% Completed

Railway crossing by Push through method in progress.

Koothuparamba Proj AE 2
Date: 02/03/2022

Work in progress | 98% Completed

Railway crossing by Push through method started .But slow progress due to sobsoil water

Koothuparamba Proj AE 2
Date: 27/02/2022

Work in progress | 98% Completed

Railway crossing by Push through method started but slow progress due to sub soil water

Koothuparamba Proj AE 2
Date: 24/02/2022

Work in progress | 98% Completed

Railway crossing by Push through method started but slow progress due to sub soil water

Koothuparamba Proj AE 2
Date: 21/02/2022

Work in progress | 98% Completed

Railway crossing by Push through method started but slow progress due to sub soil water

Koothuparamba Proj AE 2
Date: 14/02/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.But stopped due to high water table

Koothuparamba Proj AE 2
Date: 11/02/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.But stopped due to high water table

Koothuparamba Proj AE 2
Date: 06/02/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.But stopped due to high water table

Koothuparamba Proj AE 2
Date: 03/02/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.But stopped due to high water table

Koothuparamba Proj AE 2
Date: 31/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.But stopped due to high water table

Koothuparamba Proj AE 2
Date: 29/01/2022

Work in progress | 98% Completed

Trial pit excavation started on 25.01.2022 but stopped due to sub soil water, also waiting for caution from Southern railway, palagat division.

Koothuparamba Proj AE 2
Date: 25/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Trial pit excavation started.

Koothuparamba Proj AE 2
Date: 23/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.MS pipe stacked at site.Ready for start the work.

Koothuparamba Proj AE 2
Date: 20/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.Notice issued to contractor for making arrangements to start the work.MS pipe stacked at site.Casing pipe stacked at site today

Koothuparamba Proj AE 2
Date: 19/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Applied for Caution from Railway.Notice issued to contractor for making arrangements to start the work.MS pipe stacked at site.

Koothuparamba Proj AE 2
Date: 12/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.But notice issued to contractor for making arrangements to start the work.Expecting to start the work by 15 th of this month

Koothuparamba Proj AE 2
Date: 09/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.But notice issued to contractor for making arrangements to start the work.Expecting to start the work by 15 th of this month

Koothuparamba Proj AE 2
Date: 05/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.But notice issued to contractor for making arrangements to start the work.Expecting to start the work by 15 th of this month

Koothuparamba Proj AE 2
Date: 03/01/2022

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 31/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 27/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 23/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 19/12/2021

Work in progress | 98% Completed

ail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 16/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 13/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 10/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.But notice issued to contractor for making arrangements to start the work.

Koothuparamba Proj AE 2
Date: 06/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.

Koothuparamba Proj AE 2
Date: 02/12/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.

Koothuparamba Proj AE 2
Date: 28/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.MD visited the site 0n 23 rd ,then convinced the present situation due to water logging at site.

Koothuparamba Proj AE 2
Date: 25/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 19/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 17/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 15/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 13/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 11/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 09/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 07/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 04/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 02/11/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 31/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 29/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 27/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 25/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 21/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway.Water logged area ,hence at present can not do the work.

Koothuparamba Proj AE 2
Date: 19/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 16/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 13/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 11/10/2021

Work in progress | 98% Completed

ail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 09/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 04/10/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 30/09/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.Applied for Caution from Railway

Koothuparamba Proj AE 2
Date: 28/09/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.

Koothuparamba Proj AE 2
Date: 25/09/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.

Koothuparamba Proj AE 2
Date: 22/09/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work. Rqusted to Railway for Caution .

Koothuparamba Proj AE 2
Date: 20/09/2021

Work in progress | 98% Completed

Rail crossing permission obtained.Letter issued to the contractor concerned to start the work.

Koothuparamba Proj AE 2
Date: 16/09/2021

Work in progress | 98% Completed

fee remitted for way leave and other charges to railway.

Koothuparamba Proj AE 2
Date: 12/09/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 08/09/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 06/09/2021

Work in progress | 98% Completed

Rail crossings permission pending

Koothuparamba Proj AE 2
Date: 03/09/2021

Work in progress | 98% Completed

rail crossing permission pending

Koothuparamba Proj AE 2
Date: 31/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 27/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 25/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 23/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 16/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 13/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 11/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 08/08/2021

Work in progress | 98% Completed

Rail crossing work pending

Koothuparamba Proj AE 2
Date: 05/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 03/08/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 01/08/2021

Work in progress | 98% Completed

rail crossing permission pending

Koothuparamba Proj AE 2
Date: 30/07/2021

Work in progress | 98% Completed

Rail crossing permission is still pending.

Koothuparamba Proj AE 2
Date: 28/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 26/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 25/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 23/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 21/07/2021

Work in progress | 98% Completed

Rail crossing permission pending.This work is the only pending work.Line charged.

Koothuparamba Proj AE 2
Date: 19/07/2021

Work in progress | 98% Completed

Rail crossing permission pending. Report from GCE kannur is not yet received. Valuation certificate asked from Railway is obtained from revenue dept and then submitted

Koothuparamba Proj AE 2
Date: 17/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 15/07/2021

Work in progress | 98% Completed

Rail crossing permission pending.As asked by Raiway authority to submit some more details ,requested to GCE kannur for the report.

Koothuparamba Proj AE 2
Date: 13/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 10/07/2021

Work in progress | 98% Completed

Waiting for railcrossing permission

Koothuparamba Proj AE 2
Date: 08/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 06/07/2021

Work in progress | 98% Completed

Rail crossing pending

Koothuparamba Proj AE 2
Date: 05/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 03/07/2021

Work in progress | 98% Completed

Rail crossing-permission pending

Koothuparamba Proj AE 2
Date: 02/07/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 01/07/2021

Work in progress | 98% Completed

Rail crossing permission still pending.A report regarding with Jackforce is requsted to GCE kannur is not received.Today also contacted with GCE authorities.Expecting the report in the next week.

Koothuparamba Proj AE 2
Date: 29/06/2021

Work in progress | 98% Completed

waiting for rail crossing permission.

Koothuparamba Proj AE 2
Date: 24/06/2021

Work in progress | 98% Completed

Waiting for Rail crossing permission

Koothuparamba Proj AE 2
Date: 23/06/2021

Work in progress | 98% Completed

Permission pending from railway.Thrust force report from GCE kannur is also pending.

Koothuparamba Proj AE 2
Date: 22/06/2021

Work in progress | 98% Completed

Rail crossing work is the only pending work.Waiting for permission from railway. Railway asked for Thrust force report Report.Requsted to Kannue Govt.engineering college for the roport . Contacted yesterday.The reporting is delayed due to absence of cocerned experts due to lock down.

Koothuparamba Proj AE 2
Date: 19/06/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 16/06/2021

Work in progress | 98% Completed

Permission for rail crossing not yet received

Koothuparamba Proj AE 2
Date: 13/06/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 09/06/2021

Work in progress | 98% Completed

Rail crossing permission not yet received

Koothuparamba Proj AE 2
Date: 01/06/2021

Work in progress | 98% Completed

Waiting for rail crossing permission.Contacted Divisional manager Palakkad.

Koothuparamba Proj AE 2
Date: 31/05/2021

Work in progress | 98% Completed

Waiting for rail crossing permission

Koothuparamba Proj AE 2
Date: 27/05/2021

Work in progress | 98% Completed

Waiting for railcrossing permission

Koothuparamba Proj AE 2
Date: 19/05/2021

Work in progress | 98% Completed

waiting for permission from Railway for crossing by push through

Koothuparamba Proj AE 2
Date: 14/05/2021

Work in progress | 98% Completed

Waiting for crossing permission from railway

Koothuparamba Proj AE 2
Date: 11/05/2021

Work in progress | 98% Completed

waitng for permission from railway

Koothuparamba Proj AE 2
Date: 07/05/2021

Work in progress | 98% Completed

Permission to rail crossing is pending

Koothuparamba Proj AE 2
Date: 03/05/2021

Work in progress | 98% Completed

Waiting for permission from railway

Koothuparamba Proj AE 2
Date: 27/04/2021

Work in progress | 98% Completed

Waiting for permission from Railway for push through.

Koothuparamba Proj AE 2
Date: 23/04/2021

Work in progress | 98% Completed

Waiting for permission from railway.Design drawing submitted to HO of Southern Railway.Chennai

Koothuparamba Proj AE 2
Date: 20/04/2021

Work in progress | 98% Completed

Railway crossing permission to be obtained

Koothuparamba Proj AE 2
Date: 19/04/2021

Work in progress | 98% Completed

Waiting for railway crossing permission

Koothuparamba Proj AE 2
Date: 13/04/2021

Work in progress | 98% Completed

waiting for raiway crossing permission

Koothuparamba Proj AE 2
Date: 09/04/2021

Work in progress | 98% Completed

Waiting for permission from Railway

Koothuparamba Proj AE 2
Date: 03/04/2021

Work in progress | 98% Completed

Detailed drawing submitted to HQ of railway by Palakkad Division

Koothuparamba Proj AE 2
Date: 31/03/2021

Work in progress | 98% Completed

Agreement executed with Railway for getting permission.Valuation of land is also to be submitted by village office Kannur 1.applied for valuation certificate

Koothuparamba Proj AE 2
Date: 27/03/2021

Work in progress | 98% Completed

Permission for railcrossing is not yet received

Koothuparamba Proj AE 2
Date: 24/03/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 22/03/2021

Work in progress | 98% Completed

Rail crossing permission pending

Koothuparamba Proj AE 2
Date: 18/03/2021

Work in progress | 98% Completed

Rail crossing permission not obtained

Koothuparamba Proj AE 2
Date: 16/03/2021

Work in progress | 98% Completed

Rail crossing permission still pending

Koothuparamba Proj AE 2
Date: 14/03/2021

Work in progress | 98% Completed

Railway crossing still pending

Koothuparamba Proj AE 2
Date: 11/03/2021

Work in progress | 98% Completed

Permissin for rail crossing is still pending

Koothuparamba Proj AE 2
Date: 09/03/2021

Work in progress | 98% Completed

Permission for rail crossing is still pending

Koothuparamba Proj AE 2
Date: 05/03/2021

Work in progress | 98% Completed

Waiting for rail crossing permission

Koothuparamba Proj AE 2
Date: 02/03/2021

Work in progress | 98% Completed

Rail crossing work pending for permission

Koothuparamba Proj AE 2
Date: 23/02/2021

Work in progress | 98% Completed

Rail crossing permission still pending

Koothuparamba Proj AE 2
Date: 18/02/2021

Work in progress | 98% Completed

Raiway crossing permission still pending

Koothuparamba Proj AE 2
Date: 12/02/2021

Work in progress | 98% Completed

Railway crossing permission to be obtained

Koothuparamba Proj AE 2
Date: 11/02/2021

Work in progress | 98% Completed

Railway crossing permission awaited

Koothuparamba Proj AE 2
Date: 08/02/2021

Work in progress | 98% Completed

All other works completed except railway crossing which permission awaiting

Koothuparamba Proj AE 2
Date: 03/02/2021

Work in progress | 98% Completed

Railway crossing permission to be obtained

Koothuparamba Proj AE 2
Date: 02/02/2021

Work in progress | 98% Completed

Railway crossing permission to be obtained

Koothuparamba Proj AE 2
Date: 26/01/2021

Work in progress | 98% Completed

Trial pit taken on both side of Railway track for starting the railway crossing. water met just below the ground.Hence stopped further digging.

Koothuparamba Proj AE 2
Date: 14/09/2020

Work in progress | 98% Completed

Work completed except a railway crossing .

Koothuparamba Proj AE 2
Date: 24/08/2020

Work in progress | 97% Completed

2.63kms of 350mm DI gravity main and 3.825kms of 300mm DI pumping main all works completed except railway crossing work at Chovva. All other works including construction of pump house,erection of pump sets etc. are completed.