Kozhikode PH Dn EE
Date: 20/03/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 11/02/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 22/01/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 20/01/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 10/01/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 03/01/2025

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 11/12/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 07/12/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 02/12/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 27/11/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 22/11/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 19/11/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 16/11/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 13/11/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 11/11/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 08/11/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 29/10/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 19/10/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 28/09/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 19/09/2024

Work has been completed | 100% Completed

Final bill submitted.

Kozhikode PH Dn EE
Date: 10/09/2024

Work has been completed | 100% Completed

Final bill submitted

Kozhikode PH Dn EE
Date: 21/08/2024

Work has been completed | 100% Completed

RE submitted

Kozhikode PH Dn EE
Date: 27/06/2024

Work has been completed | 100% Completed

completed

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 95% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 55% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 53% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 50% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 48% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 45% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 43% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 40% Completed

Work in progress. 800 M Laid ,102 FHTC

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 34% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/10/2023

Work in progress | 30% Completed

Work started

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 25% Completed

Work started

Kozhikode PH Dn EE
Date: 14/09/2023

Work in progress | 15% Completed

Work started

Kozhikode PH Dn EE
Date: 05/09/2023

Work in progress | 10% Completed

Work started

Kozhikode PH Dn EE
Date: 17/08/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 08/08/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 24/07/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Work order issued

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Work order issued

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Work order issued

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

LOA Submit for Aprovel

Kozhikode PH Dn EE
Date: 07/06/2023

Work has started | 0% Completed

Work Tendered