| Painavu PH Section AE |
| Date: 31/05/2023 |
Work has been completed | 100% Completed
CC Ist & Bill Submitted
| Painavu PH Section AE |
| Date: 09/03/2023 |
Work in progress | 91% Completed
Bill under preparation
| Painavu PH Section AE |
| Date: 27/02/2023 |
Work in progress | 90% Completed
Bill under preparation
| Painavu PH Section AE |
| Date: 21/02/2023 |
Work in progress | 89% Completed
Line Charging completed
| Painavu PH Section AE |
| Date: 14/02/2023 |
Work in progress | 87% Completed
Line Charging Works going on
| Painavu PH Section AE |
| Date: 06/02/2023 |
Work in progress | 85% Completed
Pipe Laying Completed
| Painavu PH Section AE |
| Date: 04/02/2023 |
Work in progress | 84% Completed
Pipe laying is almost finished
| Painavu PH Section AE |
| Date: 25/01/2023 |
Work in progress | 80% Completed
Pipe Laying work is almost completed
| Painavu PH Section AE |
| Date: 20/01/2023 |
Work in progress | 75% Completed
Pipe Laying work is almost done
| Painavu PH Section AE |
| Date: 10/01/2023 |
Work in progress | 75% Completed
75% of Pipe laying Completed
| Painavu PH Section AE |
| Date: 04/01/2023 |
Work in progress | 68% Completed
Pipe laying work is going on
| Painavu PH Section AE |
| Date: 26/12/2022 |
Work in progress | 64% Completed
Pipe Laying Work in Progress
| Painavu PH Section AE |
| Date: 17/12/2022 |
Work in progress | 61% Completed
Pipe Laying in Progress
| Painavu PH Section AE |
| Date: 13/12/2022 |
Work in progress | 60% Completed
Pipe Laying Works in Progress
| Painavu PH Section AE |
| Date: 08/12/2022 |
Work in progress | 58% Completed
Work in progress
| Painavu PH Section AE |
| Date: 03/12/2022 |
Work in progress | 53% Completed
Work on going
| Painavu PH Section AE |
| Date: 29/11/2022 |
Work in progress | 50% Completed
Work on going
| Painavu PH Section AE |
| Date: 24/11/2022 |
Work in progress | 45% Completed
Work on going
| Painavu PH Sub Dn AEE |
| Date: 23/11/2022 |
Work in progress | 20% Completed
work in progress
| Painavu PH Section AE |
| Date: 16/11/2022 |
Work in progress | 10% Completed
Pipe supply done, work started
| Painavu PH Sub Dn AEE |
| Date: 06/11/2022 |
Work in progress | 5% Completed
work in progress
| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has started | 0% Completed
pipe tested on 14.10.22
| Painavu PH Section AE |
| Date: 03/10/2022 |
Work in progress | 0% Completed
Agreement executed, pipe supply not done
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has started | 0% Completed
pipe supply order placed in the firm.
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has started | 0% Completed
Agreement Executed
| Painavu PH Sub Dn AEE |
| Date: 15/09/2022 |
Work has started | 0% Completed
Agreement Executed
| Painavu PH Section AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 01/09/2022 |
Work has started | 0% Completed
work order issued
| Thodupuzha PH Dn EE |
| Date: 27/08/2022 |
Work has started | 0% Completed
Work Order Issued