Irinjalakkuda PH Dn EE |
Date: 01/11/2021 |
Work has been completed | 100% Completed
FCC paid
Irinjalakkuda PH Dn EE |
Date: 11/07/2021 |
Work has been completed | 100% Completed
Work completed. Final bill submitted to HO
Irinjalakkuda PH Dn EE |
Date: 07/07/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 06/07/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 02/07/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 28/06/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 25/06/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 15/06/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 11/06/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 07/06/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 30/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 29/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 25/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 23/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 17/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 09/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 08/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 07/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 06/05/2021 |
Work has been completed | 100% Completed
Forth and part bill paid 452945/-
Irinjalakkuda PH Dn EE |
Date: 04/05/2021 |
Work has been completed | 100% Completed
Total bill paid 1931147/-
Irinjalakkuda PH Dn EE |
Date: 30/04/2021 |
Work has been completed | 100% Completed
Paid up to Third part bill (total 1950541/-)
Irinjalakkuda PH Dn EE |
Date: 29/04/2021 |
Work has been completed | 100% Completed
completed
Irinjalakkuda PH Dn EE |
Date: 26/04/2021 |
Work has been completed | 100% Completed
completed
Irinjalakkuda PH Dn EE |
Date: 30/03/2021 |
Work in progress | 85% Completed
256 nos completed
Irinjalakkuda PH Dn EE |
Date: 22/03/2021 |
Work in progress | 85% Completed
256 nos completed
Irinjalakkuda PH Dn EE |
Date: 19/03/2021 |
Work in progress | 85% Completed
256 nos completed
Irinjalakkuda PH Dn EE |
Date: 17/03/2021 |
Work in progress | 77% Completed
CC Second and part bill under scrutiny.
Irinjalakkuda PH Dn EE |
Date: 15/03/2021 |
Work in progress | 77% Completed
CC First part bill submitted to H.O (RS. 455088/-)
Irinjalakkuda PH Dn EE |
Date: 10/03/2021 |
Work in progress | 77% Completed
77 % completed
Irinjalakkuda PH Dn EE |
Date: 09/03/2021 |
Work in progress | 77% Completed
77 % completed
Irinjalakkuda PH Dn EE |
Date: 05/03/2021 |
Work in progress | 73% Completed
First part bill submitted .
Irinjalakkuda PH Dn EE |
Date: 01/03/2021 |
Work in progress | 73% Completed
First part bill submitted .
Irinjalakkuda PH Dn EE |
Date: 26/02/2021 |
Work in progress | 73% Completed
First part bill submitted .
Irinjalakkuda PH Dn EE |
Date: 22/02/2021 |
Work in progress | 73% Completed
First part bill submitted .
Irinjalakkuda PH Dn EE |
Date: 19/02/2021 |
Work in progress | 73% Completed
73 % completed.
Irinjalakkuda PH Dn EE |
Date: 17/02/2021 |
Work in progress | 73% Completed
73% completed.
Irinjalakkuda PH Dn EE |
Date: 16/02/2021 |
Work in progress | 71% Completed
71 % COMPLETED
Irinjalakkuda PH Dn EE |
Date: 10/02/2021 |
Work in progress | 70% Completed
215 Nos completed