Irinjalakkuda PH Dn EE
Date: 01/11/2021

Work has been completed | 100% Completed

FCC paid

Irinjalakkuda PH Dn EE
Date: 11/07/2021

Work has been completed | 100% Completed

Work completed. Final bill submitted to HO

Irinjalakkuda PH Dn EE
Date: 07/07/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 06/07/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 02/07/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 28/06/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 25/06/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 15/06/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 11/06/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 07/06/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 30/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 29/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 25/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 23/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 17/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 09/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 08/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 07/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 06/05/2021

Work has been completed | 100% Completed

Forth and part bill paid 452945/-

Irinjalakkuda PH Dn EE
Date: 04/05/2021

Work has been completed | 100% Completed

Total bill paid 1931147/-

Irinjalakkuda PH Dn EE
Date: 30/04/2021

Work has been completed | 100% Completed

Paid up to Third part bill (total 1950541/-)

Irinjalakkuda PH Dn EE
Date: 29/04/2021

Work has been completed | 100% Completed

completed

Irinjalakkuda PH Dn EE
Date: 26/04/2021

Work has been completed | 100% Completed

completed

Irinjalakkuda PH Dn EE
Date: 30/03/2021

Work in progress | 85% Completed

256 nos completed

Irinjalakkuda PH Dn EE
Date: 22/03/2021

Work in progress | 85% Completed

256 nos completed

Irinjalakkuda PH Dn EE
Date: 19/03/2021

Work in progress | 85% Completed

256 nos completed

Irinjalakkuda PH Dn EE
Date: 17/03/2021

Work in progress | 77% Completed

CC Second and part bill under scrutiny.

Irinjalakkuda PH Dn EE
Date: 15/03/2021

Work in progress | 77% Completed

CC First part bill submitted to H.O (RS. 455088/-)

Irinjalakkuda PH Dn EE
Date: 10/03/2021

Work in progress | 77% Completed

77 % completed

Irinjalakkuda PH Dn EE
Date: 09/03/2021

Work in progress | 77% Completed

77 % completed

Irinjalakkuda PH Dn EE
Date: 05/03/2021

Work in progress | 73% Completed

First part bill submitted .

Irinjalakkuda PH Dn EE
Date: 01/03/2021

Work in progress | 73% Completed

First part bill submitted .

Irinjalakkuda PH Dn EE
Date: 26/02/2021

Work in progress | 73% Completed

First part bill submitted .

Irinjalakkuda PH Dn EE
Date: 22/02/2021

Work in progress | 73% Completed

First part bill submitted .

Irinjalakkuda PH Dn EE
Date: 19/02/2021

Work in progress | 73% Completed

73 % completed.

Irinjalakkuda PH Dn EE
Date: 17/02/2021

Work in progress | 73% Completed

73% completed.

Irinjalakkuda PH Dn EE
Date: 16/02/2021

Work in progress | 71% Completed

71 % COMPLETED

Irinjalakkuda PH Dn EE
Date: 10/02/2021

Work in progress | 70% Completed

215 Nos completed