Thrissur WW Sn - AE 1
Date: 28/06/2024

Work in progress | 29% Completed

IX - RCC column up to plinth beam work ongoing.

Thrissur WW Sn - AE 1
Date: 25/06/2024

Work in progress | 29% Completed

IX - RCC column up to plinth beam work ongoing.

Thrissur WW Sn - AE 1
Date: 24/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 21/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 18/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 13/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 10/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 05/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 03/06/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur PH Dn EE
Date: 30/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 27/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 23/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 18/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 14/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 10/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 06/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 04/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 02/05/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 30/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 29/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 27/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur PH Dn EE
Date: 25/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 23/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur PH Dn EE
Date: 19/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 16/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 15/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur PH Dn EE
Date: 12/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 08/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed

Thrissur WW Sn - AE 1
Date: 03/04/2024

Work in progress | 6% Completed

IX - RCC column up to plinth beam completed.

Thrissur WW Sn - AE 1
Date: 01/04/2024

Work in progress | 6% Completed

RCC Column footing completed, 28th DAY Cube testing is in progress.

Thrissur WW Sn - AE 1
Date: 30/03/2024

Work in progress | 6% Completed

RCC Column footing completed, 14th DAY Cube testing is progress.

Thrissur WW Sn - AE 1
Date: 26/03/2024

Work in progress | 6% Completed

RCC Column footing completed, 14th DAY Cube testing is progress.

Thrissur PH Dn EE
Date: 23/03/2024

Work in progress | 6% Completed

RCC Column footing completed, 7TH DAY Cube testing is progress.

Thrissur WW Sn - AE 1
Date: 19/03/2024

Work in progress | 6% Completed

RCC Column footing completed, 7TH DAY Cube testing is progress.

Thrissur WW Sn - AE 1
Date: 15/03/2024

Work in progress | 6% Completed

RCC Column footing completed, 7TH DAY Cube testing is progress.

Thrissur PH Dn EE
Date: 14/03/2024

Work in progress | 5% Completed

RCC Column footing completed.

Thrissur WW Sn - AE 1
Date: 11/03/2024

Work in progress | 5% Completed

RCC Column footing completed

Thrissur WW Sn - AE 1
Date: 05/03/2024

Work in progress | 5% Completed

RCC Column footing completed

Thrissur WW Sn - AE 1
Date: 29/02/2024

Work in progress | 5% Completed

Footing PCC completed

Thrissur WW Sn - AE 1
Date: 26/02/2024

Work in progress | 5% Completed

Steel reinforcement work in progress. Earthwork completed.

Thrissur WW Sn - AE 1
Date: 23/02/2024

Work in progress | 5% Completed

Steel reinforcement started. Earthwork completed.

Thrissur WW Sn - AE 1
Date: 19/02/2024

Work in progress | 3% Completed

work in progress

Thrissur WW Sn - AE 1
Date: 15/02/2024

Work in progress | 3% Completed

Structural design submitted to AEE & EE for approval

Thrissur WW Sn - AE 1
Date: 12/02/2024

Work in progress | 3% Completed

Structural design submitted to AEE & EE for approval

Thrissur WW Sn - AE 1
Date: 08/02/2024

Work in progress | 3% Completed

Structural design submitted to AEE & EE for approval

Thrissur WW Sn - AE 1
Date: 06/02/2024

Work in progress | 3% Completed

Structural design submitted to AEE & EE for approval

Thrissur WW Sn - AE 1
Date: 02/02/2024

Work in progress | 3% Completed

Structural design submitted to AEE & EE for approval

Thrissur WW Sn - AE 1
Date: 29/01/2024

Work in progress | 3% Completed

Earth work -Work in progress

Thrissur WW Sn - AE 1
Date: 25/01/2024

Work in progress | 3% Completed

Earth work -Work in progress

Thrissur WW Sn - AE 1
Date: 22/01/2024

Work in progress | 3% Completed

Design completed, Earth work started

Thrissur WW Sn - AE 1
Date: 18/01/2024

Work in progress | 2% Completed

Site handover

Thrissur WW Sn - AE 1
Date: 16/01/2024

Work in progress | 2% Completed

Site handover

Thrissur WW Sn - AE 1
Date: 11/01/2024

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 08/01/2024

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 03/01/2024

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 01/01/2024

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 28/12/2023

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 26/12/2023

Work in progress | 2% Completed

Design obtained,work in progress

Thrissur WW Sn - AE 1
Date: 21/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 18/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 14/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 11/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 07/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 04/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 01/12/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur WW Sn - AE 1
Date: 28/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.Design under preparation.

Thrissur PH Dn EE
Date: 24/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.

Thrissur WW Sn - AE 1
Date: 20/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.

Thrissur WW Sn - AE 1
Date: 16/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.

Thrissur WW Sn - AE 1
Date: 13/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site handover.

Thrissur WW Sn - AE 1
Date: 09/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 06/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur PH Dn EE
Date: 03/11/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 30/10/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur PH Dn EE
Date: 28/10/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur PH Dn EE
Date: 25/10/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 19/10/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 16/10/2023

Work in progress | 2% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur PH Dn EE
Date: 14/10/2023

Work in progress | 1% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 12/10/2023

Work in progress | 1% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur PH Dn EE
Date: 09/10/2023

Work in progress | 1% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023. Site hand over.

Thrissur WW Sn - AE 1
Date: 04/10/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 30/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 27/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur WW Sn - AE 1
Date: 26/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 25/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 23/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 22/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 19/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 15/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023

Thrissur PH Dn EE
Date: 14/09/2023

Work has started | 0% Completed

Work order issued on 14.08.2023 & Agreement executed on 23.08.2023.