| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has been completed | 100% Completed
Completed
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has been completed | 100% Completed
completed
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has been completed | 100% Completed
Completed
| Painavu PH Sub Dn AEE |
| Date: 04/08/2022 |
Work has been completed | 100% Completed
Completed
| Painavu PH Sub Dn AEE |
| Date: 01/08/2022 |
Work has been completed | 100% Completed
completed
| Painavu PH Section AE |
| Date: 12/04/2022 |
Work has been completed | 100% Completed
work completed
| Painavu PH Section AE |
| Date: 08/04/2022 |
Work has been completed | 100% Completed
work completed
| Painavu PH Section AE |
| Date: 04/04/2022 |
Work in progress | 82% Completed
ongoing
| Painavu PH Section AE |
| Date: 31/03/2022 |
Work in progress | 80% Completed
on going
| Painavu PH Sub Dn AEE |
| Date: 28/03/2022 |
Work in progress | 75% Completed
Work in progress ,75% completed.
| Painavu PH Section AE |
| Date: 24/03/2022 |
Work in progress | 60% Completed
on going
| Painavu PH Section AE |
| Date: 21/03/2022 |
Work in progress | 50% Completed
ongoing
| Painavu PH Section AE |
| Date: 09/03/2022 |
Work has started | 0% Completed
work tendered
| Painavu PH Section AE |
| Date: 03/03/2022 |
Work has started | 0% Completed
work tendred
| Painavu PH Section AE |
| Date: 26/02/2022 |
Work has started | 0% Completed
work tendered
| Thodupuzha PH Dn EE |
| Date: 06/02/2022 |
Work has started | 0% Completed
work Tendered Agreement not executed