Jal Jeevan Mission (JJM)-Jal Jeevan Mission-2020-21- Amboori G P-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank.-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank-General Civil Work-Nil

Project Jal Jeevan Mission (JJM)-Jal Jeevan Mission-2020-21- Amboori G P-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank.-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank-General Civil Work-Nil
Project Code TVMJJM08205578P4
Type Package
Main Project Jaljeevan Mission-2020-21-Thiruvananthapuram District-Amboori Grama Panchayath-Water supply line extension & providing water supply connections from existing and propsed pipelines to households of Amboori grama Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal Jeevan Mission-2020-21- Amboori G P-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank.-Supplying and fixing booster pump for boosting water from Thekkupara Community Centre to connect PVC Tank-General Civil Work-Nil
Status On-going
District Thiruvananthapuram
Executing Office Kattakada WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1926890
TS Number WRD/KWA-CE(SR)/TR/17393/2023_5_1_1/1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/03/2022
Scheduled date of Completion as per agreement 31 Mar 2024
Expected date of Completion 31/03/2022

Processing Dates

TS Date 31 Jul 2023
Estimate Approval 31 Jul 2023
NIT Approval 01 Jun 2023
Tender Closing 03 Jul 2023
Technichal Pre-Qualification 03 Jul 2023
Price bid opening 10 Jul 2023

Approval Dates

Workorder Date 14 Aug 2023
NA 14 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Neyyattinkara WS Dn EE
Date: 26/06/2024

Work in progress | 99% Completed

on going.

Neyyattinkara WS Dn EE
Date: 22/06/2024

Work in progress | 99% Completed

on going.