JJM -2022-23 -WSS to Chazhur Panchayath - Phase II - Providing distribution network Grama Panchayath ( Phase II) - Providing FHTCs to Rural Households by Augmentation of existing schemes.

Project JJM -2022-23 -WSS to Chazhur Panchayath - Phase II - Providing distribution network Grama Panchayath ( Phase II) - Providing FHTCs to Rural Households by Augmentation of existing schemes.
Project Code TCRJJM092113376P1
Type Package
Main Project JJM -2022-23 -WSS to Chazhur Panchayath - Phase II - Providing distribution network Grama Panchayath ( Phase II) - Providing FHTCs to Rural Households by Augmentation of existing schemes .
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM -2022-23 -WSS to Chazhur Panchayath - Phase II - Providing distribution network Grama Panchayath ( Phase II) - Providing FHTCs to Rural Households by Augmentation of existing schemes.
Status On-going
District Thrissur
Executing Office Nattika Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 213200000
TS Number TS/1983/2022511
Technical specification JJM -2022-23 -WSS to Chazhur Panchayath - Phase II - Providing distribution network Grama Panchayath ( Phase II) - Providing FHTCs to Rural Households by Augmentation of existing schemes.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/11/2022
Scheduled date of Completion as per agreement 22 Nov 2023
Expected date of Completion 22/11/2023

Processing Dates

TS Date 06 Aug 2022
Estimate Approval 06 Aug 2022
NIT Approval 15 Aug 2022
Tender Closing 31 Aug 2022
Technichal Pre-Qualification 06 Aug 2022
Price bid opening 16 Aug 2022

Approval Dates

Workorder Date 22 Nov 2022
NA 09 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Nattika Project Dn AE 6
Date: 28/06/2024

Work in progress | 72% Completed

Pipe laying & HTC Works in progress.

Nattika Project Dn AE 6
Date: 27/06/2024

Work in progress | 72% Completed

Pipe laying & HTC Works in progress.