| Project | Jal Jeevan Mission- Providing FHTC at Ummannoor Grama panchayath in Kollam District |
|---|---|
| Project Code | KLMJJM08203133P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission- Providing FHTC at Ummannoor Grama panchayath in Kollam I District |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission- Providing FHTC at Ummannoor Grama panchayath in Kollam District |
| Status | On-going |
| District | Kollam |
| Executing Office | Valakom PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 221200000 |
| TS Number | TS/2020-2021/2020/19662 |
| Technical specification | Pipe Laying work & Providing FHTCS |
| Contractor | Saidax-Vasco-lcgc-jv (Mob: 9447057937) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 05/03/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 21 Feb 2022 |
| Expected date of Completion | 30/04/2025 |
| TS Date | 07 Sep 2020 |
|---|---|
| Estimate Approval | 07 Sep 2020 |
| Tender Closing | 03 Nov 2020 |
| Technichal Pre-Qualification | 16 Nov 2020 |
| Price bid opening | 06 Nov 2020 |
| Workorder Date | 18 Dec 2020 |
|---|---|
| NA | 22 Feb 2021 |
| Valakom PH Sn AE |
| Date: 18/06/2025 |
Work has been completed | 100% Completed
work completed on 28/02/24.
| Valakom PH Sn AE |
| Date: 16/04/2025 |
Work in progress | 71% Completed
89km pipe Laying work and 6334 FHTC completed. providing FHTC in ward of additional pipe laying work.