Jal Jeevan Mission (JJM)-WSS to Puthur ,Pananchery and Madakkathara panchayath (7th SWSM)-(Package 2)-Supply, installation, testing and commissioning of Floating intake structure and Motor Pump set at Peechi reservoir for pumping to 36 MLD WTP at Peechi.-Pipeline Work

Project Jal Jeevan Mission (JJM)-WSS to Puthur ,Pananchery and Madakkathara panchayath (7th SWSM)-(Package 2)-Supply, installation, testing and commissioning of Floating intake structure and Motor Pump set at Peechi reservoir for pumping to 36 MLD WTP at Peechi.-Pipeline Work
Project Code TCRJJM102315878P1
Type Package
Main Project Jal Jeevan Mission (JJM)-WSS to Puthur ,Pananchery and Madakkathara panchayath (7th SWSM)-(Package 2)-Supply, installation, testing and commissioning of Floating intake structure and Motor Pump set at Peechi reservoir for pumping to 36 MLD WTP at Peechi.-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-WSS to Puthur ,Pananchery and Madakkathara panchayath (7th SWSM)-(Package 2)-Supply, installation, testing and commissioning of Floating intake structure and Motor Pump set at Peechi reservoir for pumping to 36 MLD WTP at Peechi.-Pipeline Work
Status On-going
District Thrissur
Executing Office Peechi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 15800000
TS Number WRD/KWA-CE(CR)/EST_TS/17647/2023_26_1_1 Dated: 07-12-2023
Technical specification (Package 2)-Supply, installation, testing and commissioning of Floating intake structure and Motor Pump set at Peechi reservoir for pumping to 36 MLD WTP at Peechi.-Pipeline Work
Contractor Tony.P.Thekiniyath (Mob: 9447032035)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/02/2024
Scheduled date of Completion as per agreement 08 Aug 2024
Expected date of Completion 08/08/2024

Processing Dates

TS Date 07 Dec 2023
Estimate Approval 07 Dec 2023
NIT Approval 10 Jan 2024
Tender Closing 19 Jan 2024
Technichal Pre-Qualification 19 Jan 2024
Price bid opening 20 Jan 2024

Approval Dates

Workorder Date 09 Feb 2024
NA 23 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Peechi PH Sn - AE
Date: 26/06/2024

Work in progress | 2% Completed

Work order issued on 09.02.2024. Agreement executed on 23.02.2024. Letter given for pipe testing & motor inspection on 25.04.2024. .

Peechi PH Sn - AE
Date: 24/06/2024

Work in progress | 2% Completed

Work order issued on 09.02.2024. Agreement executed on 23.02.2024. Letter given for pipe testing & motor inspection on 25.04.2024. .