Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - PUZHATHI ZONE- Pipeline work

Project AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - PUZHATHI ZONE- Pipeline work
Project Code KNRAMRUT 2032314171
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - PUZHATHI ZONE- Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 699900000
AS Number G.O (Rt)No.677/2023/LSGD
TS Amount (Rs) 89500000
TS Number WRD/KWA-CE(NR)/EST-TS/674/2022-26-1-1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - PUZHATHI ZONE- Pipeline work Kannur WS Sn 3

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jun 2024 12.5 km pipe laid 1120 connections given Kannur PH Sn 3 AE
18 May 2024 12 km pipe laid 1110 connections given Kannur PH Sn 3 AE
02 May 2024 11.9 km pipe laid 1100 connections given Kannur PH Sn 3 AE
18 Apr 2024 60% Completed, Pipe laid-11.7 km , FHTC - 1080 Kannur PH Sn 3 AE
21 Mar 2024 WORK IN PROGRESS Kannur PH Sn 3 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 21 Mar 2023
TS Date 10 Apr 2023

Other details

Project Officers View