Jal Jeevan Mission (JJM)-2020-2021-Phase -I Balance Work-Mulakkulam Panchayath -Relaying of existing 315 mm PVC pipe line with 300mm DI Pipe line along Rajankavala-Arunoottimangalam Road in Mulakkulam panchayath

Project Jal Jeevan Mission (JJM)-2020-2021-Phase -I Balance Work-Mulakkulam Panchayath -Relaying of existing 315 mm PVC pipe line with 300mm DI Pipe line along Rajankavala-Arunoottimangalam Road in Mulakkulam panchayath
Project Code KTMJJM08204322P3
Type Package
Main Project JJM-(Phase - I) - 2020-21-Mulakkulam Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-2020-2021-Phase -I Balance Work-Mulakkulam Panchayath -Relaying of existing 315 mm PVC pipe line with 300mm DI Pipe line along Rajankavala-Arunoottimangalam Road in Mulakkulam panchayath
Status Completed
District Kottayam
Executing Office Peruva Sn
Agreement Number
Agreement Date
TS Amount (Rs) 22600000
TS Number WRD/KWA-CE (SR)/EST_TS/633/2022_26_1_1 Dated 01-11-2022
Technical specification Relaying of existing 315 mm PVC pipe line with 300mm DI Pipe line along Rajankavala-Arunoottimangalam Road in Mulakkulam panchayath
Contractor K G Eldhose (Mob: 9447433381)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/02/2023
Scheduled date of Completion as per agreement 31 May 2023
Expected date of Completion 31/05/2023

Processing Dates

TS Date 01 Nov 2022
Estimate Approval 01 Nov 2022
NIT Approval 29 Oct 2022
Tender Closing 11 Nov 2022
Technichal Pre-Qualification 29 Oct 2022
Price bid opening 14 Nov 2022

Approval Dates

Workorder Date 01 Dec 2022
NA 19 Dec 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaduthuruthy Dn EE
Date: 11/04/2024

Work has been completed | 100% Completed

Work completed.Bill Submitted .

Kaduthuruthy Dn EE
Date: 10/04/2024

Work has been completed | 100% Completed

Work completed.Bill Submitted .