JJM Providing FHTCs to Kuttippuram ,Thirunnavaya,Athavanad and Marakkara panchayaths

Project JJM Providing FHTCs to Kuttippuram ,Thirunnavaya,Athavanad and Marakkara panchayaths
Project Code MLPJJM022213232
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM Providing FHTCs to Kuttippuram ,Thirunnavaya,Athavanad and Marakkara panchayaths - including laying distribution network
Status On-going
District Malappuram
Executing Office Edappal PH Dn
AS Amount (Rs) 2210712000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 575000000
TS Number WRD/KWA-CEP/EST-TS/220/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 71500
Capacity in MLD 124.14
Actual Project Completion Date 31 Mar 2024
Coverage Kuttipuram Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM Providing FHTCs to Kuttippuram including laying distribution network and FHTCs Tirur section

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 90mm pvc 8 kg 1008 m3879m ,140mm 8kg/cm2- 537 m ,140mm tr,90mm pvc 10kg 1002mtr,75 mm/6 kg-498 mtr. are supplyed on 15/09/2023...... Laying of 200mm DI K9-2046 M,90mm 8kg/CM2-12598 M,90mm 10kg/cm2-16503 m,110 mm 8 kg/cm2-4274 m,110mm 10kg/cm2-10kg/cm2-4245m,160mm 8kg/cm2-568 m,160mm 10kg/cm2-1792 m,140mm 08kg/cm-1301m,140mm 10kg/cm-1411 m ,GI-49 m.Completed Tirur Sn AE
12 May 2024 90mm pvc 8 kg 1008 m3879m ,140mm 8kg/cm2- 537 m ,140mm tr,90mm pvc 10kg 1002mtr,75 mm/6 kg-498 mtr. are supplyed on 15/09/2023...... Laying of 200mm DI K9-2046 M,90mm 8kg/CM2-12598 M,90mm 10kg/cm2-16503 m,110 mm 8 kg/cm2-4274 m,110mm 10kg/cm2-10kg/cm2-4245m,160mm 8kg/cm2-568 m,160mm 10kg/cm2-1792 m,140mm 08kg/cm-1301m,140mm 10kg/cm-1411 m ,GI-49 m.Completed Tirur Sn AE
10 May 2024 90mm pvc 8 kg 1008 m3879m ,140mm 8kg/cm2- 537 m ,140mm tr,90mm pvc 10kg 1002mtr,75 mm/6 kg-498 mtr. are supplyed on 15/09/2023...... Laying of 200mm DI K9-2046 M,90mm 8kg/CM2-12598 M,90mm 10kg/cm2-16503 m,110 mm 8 kg/cm2-4274 m,110mm 10kg/cm2-10kg/cm2-4245m,160mm 8kg/cm2-568 m,160mm 10kg/cm2-1792 m,140mm 08kg/cm-1301m,140mm 10kg/cm-1411 m ,GI-49 m.Completed Tirur Sn AE
06 May 2024 90mm pvc 8 kg 1008 m3879m ,140mm 8kg/cm2- 537 m ,140mm tr,90mm pvc 10kg 1002mtr,75 mm/6 kg-498 mtr. are supplyed on 15/09/2023...... Laying of 200mm DI K9-2046 M,90mm 8kg/CM2-12598 M,90mm 10kg/cm2-16503 m,110 mm 8 kg/cm2-4274 m,110mm 10kg/cm2-10kg/cm2-4245m,160mm 8kg/cm2-568 m,160mm 10kg/cm2-1792 m,140mm 08kg/cm-1301m,140mm 10kg/cm-1411 m ,GI-49 m.Completed Tirur Sn AE
03 May 2024 90mm pvc 8 kg 1008 m3879m ,140mm 8kg/cm2- 537 m ,140mm tr,90mm pvc 10kg 1002mtr,75 mm/6 kg-498 mtr. are supplyed on 15/09/2023...... Laying of 200mm DI K9-2046 M,90mm 8kg/CM2-12598 M,90mm 10kg/cm2-16503 m,110 mm 8 kg/cm2-4274 m,110mm 10kg/cm2-10kg/cm2-4245m,160mm 8kg/cm2-568 m,160mm 10kg/cm2-1792 m,140mm 08kg/cm-1301m,140mm 10kg/cm-1411 m ,GI-49 m.Completed Tirur Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/03/2023
Scheduled date of Completion of the Project 31 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 06 Oct 2022

Other details