KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package IV
Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths Package IV |
Project Code |
ALPKIIFB0619496P4 |
Type |
Package |
Main Project |
KIIFB-Augmentation and Modernization of WSS to Alappuzha Municipality, Aryad, Mannanchery and Mararikulam South Panchayaths
|
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Laying Distribution lines in Alappuzha Municipality Zone 1 , Railway crossing works between Thumboli and Alleppey KM /TP 53/900 and 54/000 & Railway crossing works between Tumboli and Alleppey KM /TP 54/900 and 55/000 |
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
450300000 |
TS Number |
WRD/KWA/CE(CR)/EST TS/11657/2023 26 1 1 |
Technical specification |
Laying Distribution lines in Alappuzha Municipality Zone 1 , Railway crossing works between Thumboli and Alleppey KM /TP 53/900 and 54/000 & Railway crossing works between Tumboli and Alleppey KM /TP 54/900 and 55/000 |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
25 Oct 2021 |
Pending |
Pending |
Road Cut Related Risk |
Joint Inspection conducted with PWD for getting estimates for Road Restoration works.PWD has rejected most of the applications citing that the roads are under DLP |
No comments available. |
Pending |
25 Oct 2021 |
Pending |
Pending |
Contract Related Risks |
1.Push through between Tumboli and Aleppeystations Chainage between53/900-54/000
2.Push through between Tumboli and Aleppeystations Chainage between54/900-55/000
3.Push through between Tumboli and Aleppey stations Chainage between 55/800-55/900
4.Push through between Punnapara and Aleppeys tations Chainage between58/700-58/800 |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
Date is not specified |
Scheduled date of Completion as per agreement |
Date is not specified |
Expected date of Completion |
31/12/2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha KIIFB - AE 4 |
Date: 17/05/2024 |
Work has started | 0% Completed
Work tendered. Last date for submitting tender on 16.10.2023. No offer received. Retendered with due date 24.11.2023..No offer Received. Retendered with due date 26.12.2023.No offer received. Retendered with due date 02.02.2024. No offer received. Retendered with due date 19.02.2024. Date extended to 04.03.2024. No offer received. Date extended to 11.03.2024. No offer received. Date extended to 21.03.2024. No offer received. Date extended to 01.04.2024. No offer received. Date extended to 15.04.2024. No offer received. Date extended to 02.05.2024. No offer received. Date extended to 24.05.2024..
Alappuzha KIIFB - AE 4 |
Date: 16/05/2024 |
Work has started | 0% Completed
Work tendered. Last date for submitting tender on 16.10.2023. No offer received. Retendered with due date 24.11.2023..No offer Received. Retendered with due date 26.12.2023.No offer received. Retendered with due date 02.02.2024. No offer received. Retendered with due date 19.02.2024. Date extended to 04.03.2024. No offer received. Date extended to 11.03.2024. No offer received. Date extended to 21.03.2024. No offer received. Date extended to 01.04.2024. No offer received. Date extended to 15.04.2024. No offer received. Date extended to 02.05.2024. No offer received. Date extended to 24.05.2024..