| Project | KIIFB Deposit-Improvements to Cheruvathur -Cheemeni IT Park-Palavayal - Bheemanadi-Mukkada road by providing DG BM and BC in Kasargode district-Relaying of Pumping main and Transmission main of WSS to Naval Academy,Relaying of pumping main and distribution pipe line of WSS to Endosulphan hit area |
|---|---|
| Project Code | KNRDEPO082213745P1 |
| Type | Package |
| Main Project | KIIFB Deposit-Improvements to Cheruvathur -Cheemeni IT Park-Palavayal - Bheemanadi-Mukkada road by providing DG BM and BC in Kasargode district-Relaying of Pumping main and Transmission main of WSS to Naval Academy,Relaying of pumping main and distribution pipe line of WSS to Endosulphan hit area . |
| Funding Agency | DEPO |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | DEPO |
| Description | Relaying of Pumping main and Transmission main of WSS to Naval Academy,Relaying of pumping main and distribution pipe line of WSS to Endosulphan hit area |
| Status | On-going |
| District | Kannur |
| Executing Office | Payyannur WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 46700000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/15440/2022_26_1_1 |
| Technical specification | Relaying of Pumping main and Transmission main of WSS to Naval Academy,Relaying of pumping main and distribution pipe line of WSS to Endosulphan hit area |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 04/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 03 Aug 2023 |
| Expected date of Completion | 03/08/2023 |
| TS Date | 18 Jan 2023 |
|---|---|
| Estimate Approval | 18 Jan 2023 |
| NIT Approval | 23 Jan 2023 |
| Tender Closing | 16 Feb 2023 |
| Technichal Pre-Qualification | 20 Feb 2023 |
| Price bid opening | 27 Feb 2023 |
| Workorder Date | 04 Mar 2023 |
|---|---|
| NA | 21 Mar 2023 |
| Thaliparamba WS Dn EE |
| Date: 13/09/2023 |
Work has been completed | 100% Completed
pumping main 350mm - 1574.5 m , pumping main 250mm -1942 m , pumping main 90mm PE -2270 m , Transmission main 350 mm - 875 m , Transmission main 350 mm - 482 m.
| Thaliparamba WS Dn EE |
| Date: 11/09/2023 |
Work in progress | 90% Completed
PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING .