KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-III

Project KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package-III
Project Code PKDKIIFB1118624P3
Type Package
Main Project KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-2017-2018- CWSS to Perumatty , Pattanchery ,Nallepilly,Elappully Panchayaths in palakkad district--Phase II-Package - III- 13LL OHSR at Elappully Veterinary Hospital Compound.
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/12/2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - EE
Date: 23/08/2022

Work has started | 0% Completed

Work will be arranged under JJM. Demand notice obtained from NSS Engineering collage Palakkad, for Soil investigation..

Chittur Project Dn - AE 1
Date: 07/08/2022

Work has started | 0% Completed

Permissive sanction for land obtained on 23.06.2022, vide order No: DCPKD/778/2022-LRG2 dtd 23.06.2022, HENCE THIS WORK WILL BE ARRANGED UNDER JAL JEEVAN MISSION. LETTER HAS BEEN SUBMITTED TO NSS ENGINEERING COLLEGE, PALAKKAD FOR SOIL INVESTIGATION.