Project | Jala Jeevan Mission 2021-22- Augmentation of CWSS to Nattika Firka-PHASE II Providing Distribution Network and FHTC to Engandiyur Panchayath |
---|---|
Project Code | TCRJJM112111744P1 |
Type | Package |
Main Project | JJM-WSS TO NATTIKA FIRKA Phase II - Engandiyur Grama Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jala Jeevan Mission 2021-22- Augmentation of CWSS to Nattika Firka-PHASE II Providing Distribution Network and FHTC to Engandiyur Panchayath |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 97900000 |
TS Number | TS/2021-2022/2021/37841 |
Technical specification | Engandiyur Panchayath |
Contractor | T Mohammed Ali (Mob: 9447733327) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 03 Mar 2023 |
Expected date of Completion | 30/06/2023 |
TS Date | 25 Nov 2021 |
---|---|
Estimate Approval | 25 Nov 2021 |
NIT Approval | 25 Nov 2021 |
Tender Closing | 18 Feb 2022 |
Technichal Pre-Qualification | 25 Nov 2021 |
Price bid opening | 25 Feb 2022 |
Workorder Date | 04 Mar 2022 |
---|---|
NA | 11 Jul 2022 |
Vadanappilly AE |
Date: 24/06/2024 |
Work in progress | 71% Completed
11.85% HTC connections and 58.46% pipe laying completed (186+0/1569 HTC connections completed , 46433 m pipe laying completed out of 70880M). C C Fifth and part bill submitted. House connection works in progress..
Vadanappilly AE |
Date: 27/04/2024 |
Work in progress | 70% Completed
11.85% HTC connections and 58.46% pipe laying completed (186+0/1569 HTC connections completed , 46433 m pipe laying completed out of 70880M). C C Fifth and part bill submitted. House connection works in progress..