Jala Jeevan Mission 2021-22- Augmentation of CWSS to Nattika Firka-PHASE II Providing Distribution Network and FHTC to Engandiyur Panchayath

Project Jala Jeevan Mission 2021-22- Augmentation of CWSS to Nattika Firka-PHASE II Providing Distribution Network and FHTC to Engandiyur Panchayath
Project Code TCRJJM112111744P1
Type Package
Main Project JJM-WSS TO NATTIKA FIRKA Phase II - Engandiyur Grama Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jala Jeevan Mission 2021-22- Augmentation of CWSS to Nattika Firka-PHASE II Providing Distribution Network and FHTC to Engandiyur Panchayath
Status On-going
District Thrissur
Executing Office Vadanappalli Sn
Agreement Number
Agreement Date
TS Amount (Rs) 97900000
TS Number TS/2021-2022/2021/37841
Technical specification Engandiyur Panchayath
Contractor T Mohammed Ali (Mob: 9447733327)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/03/2022
Scheduled date of Completion as per agreement 03 Mar 2023
Expected date of Completion 30/06/2023

Processing Dates

TS Date 25 Nov 2021
Estimate Approval 25 Nov 2021
NIT Approval 25 Nov 2021
Tender Closing 18 Feb 2022
Technichal Pre-Qualification 25 Nov 2021
Price bid opening 25 Feb 2022

Approval Dates

Workorder Date 04 Mar 2022
NA 11 Jul 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vadanappilly AE
Date: 24/06/2024

Work in progress | 71% Completed

11.85% HTC connections and 58.46% pipe laying completed (186+0/1569 HTC connections completed , 46433 m pipe laying completed out of 70880M). C C Fifth and part bill submitted. House connection works in progress..

Vadanappilly AE
Date: 27/04/2024

Work in progress | 70% Completed

11.85% HTC connections and 58.46% pipe laying completed (186+0/1569 HTC connections completed , 46433 m pipe laying completed out of 70880M). C C Fifth and part bill submitted. House connection works in progress..