Jal Jeevan Mission (JJM)-JJM-Kizhakkenchery Low Level-Providing FHTCs-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM-Kizhakkenchery Low Level-Providing FHTCs-Pipeline Work
Project Code PKDJJM022314393
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM-Kizhakkenchery Low Level-Providing FHTCs-Pipeline Work
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 495040000
AS Number GO Rt 134/2022/WRD
TS Amount (Rs) 489700000
TS Number ORDER No.: WRD/KWA-CE(NR)/EST_TS/496/2022_26_1_1 Dated: 22-11-2022
Total Bill Submitted (Rs) 102103138
Total Bill Paid (Rs) 102103138
Population Benefitted 40928
Capacity in MLD 24.50
Actual Project Completion Date 31 Dec 2024
Coverage KIZHAKKENCHERY LOW LEVEL ZONE

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM-Kizhakkenchery Low Level-Providing FHTCs-Pipeline Work Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 48% Completed | 20/06/2024 DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m Chittur Project Dn - AE 3
12 Jun 2024 Work in progress | 48% Completed | 12/06/2024 DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m Chittur Project Dn - AE 3
06 Jun 2024 Work in progress | 48% Completed | 06/06/2024 DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m Chittur Project Dn - AE 3
01 Jun 2024 Work in progress | 48% Completed | 01/06/2024 DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m Chittur Project Dn - AE 3
23 May 2024 Work in progress | 48% Completed | 23/05/2024 DI and PVC work started, 60.687km pipe line laid /126km HTC 780 /4000 NOS 1)600 mm DI-1738.50m 2)400 MM DI-66M 2)90MM PVC 6Kg-49948.00m 3)500 mm DI-957.00 4)100 mm GI – 48M 5)80mm GI- 2094 M 6)110mm 8kg pvc-292 m 7)110 mm 6kg-pvc-1572 , 8)160MM PVC 6Kg-1230M 9)160MM 8 KG-780M 10)140mm pvc -108m 11)90MM PVC 10Kg- 552m 120 90MM PVC 12.5Kg- 1625m Chittur Project Dn - AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 30/03/2023
Scheduled date of Completion of the Project 29 Mar 2023
Expected date of Completion 29/03/2024

Processing Dates

AS Date 23 Feb 2023
TS Date 22 Nov 2022

Other details

Project Officers View