Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath

Project Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath
Project Code PKDJJM122012589
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description The scope of work includes Supplying, conveying, laying, jointing, field testing to specified pressure, gap linking, trial running and commissioning of Distribution lines as per PPD design and allied specials inclusive of necessary lengths of spare pipes and providing FHTCs for full coverage of the panchayaths of Chalavara Panchayath. The work also includes providing Sluice Valves - Double Flanged Valves P.N 1.6 rated, Kinetic air valves type DS1 with flanges, construction of valve chambers for sluice valve, Air valves, Zero Velocity valves, providing R.C.C anchor blocks, RCC Identification Blocks, 200 mm dia Protection Tubes, providing C.I man hole cover, Supporting Steel Structure for Canal crossing / River Crossing / Water Way crossing and all related incidental works. Temporary road restoration shall be done by contractor. In the event of B.T cutting of PWD roads / major panchayath road junctions for road crossing, the pipe line trench shall be filled with GSB after an earth cushion of 0.3 m Newly laid pipe lines shall be linked with the existing network using necessary Tees. Any M.S fabrication works required for linking with existing lines. is included in the scope of work. Supporting Steel bridge for Canal crossing / River Crossing / Water Way crossing shall be designed and constructed by the contractor.
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 1878100000
AS Number 777
TS Amount (Rs) 401500000
TS Number TS/2021-2022/2021/44403 and TS/2022-2023/2022/17630
Total Bill Submitted (Rs) 73706885
Total Bill Paid (Rs) 73706885
Population Benefitted 30536
Capacity in MLD 22.00
Actual Project Completion Date 30 Jun 2024
Coverage Chalavara Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 120.642/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.90MM 10 KG LAYING WORK AT VEMBALATHUPADAM ON BLUECHIP CRUSHER ROAD. Palakkad Project Dn AE 4
08 May 2024 120.642/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.90MM 10 KG LAYING WORK AT VEMBALATHUPADAM ON BLUECHIP CRUSHER ROAD. Palakkad Project Dn AE 4
06 May 2024 120.481/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.CULVERT CROSSING WORK NEAR BLUECHIP CRUSHER AT VEMBALATHUPADAM ON VANIYAMKULAM VALLAPUZHA PWD ROAD Palakkad Project Dn AE 4
04 May 2024 119.805/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.IRISH BREAKING WORK AT KAYILAD ON VANIYAMKULAM VALLAPUZHA PWD ROAD Palakkad Project Dn AE 4
02 May 2024 119.805/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.PWD road cutting Permission not issued. Palakkad Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/08/2022
Scheduled date of Completion of the Project 25 Aug 2023
Expected date of Completion 30/06/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 25 Jan 2022

Other details

Project Officers View