- Home
- Jal Jeevan Mission 2021-22- Supplying, l...
Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath
Project |
Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath |
Project Code |
PKDJJM122012589 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
The scope of work includes Supplying, conveying, laying, jointing, field testing to specified pressure, gap linking, trial running and commissioning of Distribution lines as per PPD design and allied specials inclusive of necessary lengths of spare pipes and providing FHTCs for full coverage of the panchayaths of Chalavara Panchayath. The work also includes providing Sluice Valves - Double Flanged Valves P.N 1.6 rated, Kinetic air valves type DS1 with flanges, construction of valve chambers for sluice valve, Air valves, Zero Velocity valves, providing
R.C.C anchor blocks, RCC Identification Blocks, 200 mm dia Protection Tubes, providing C.I man hole cover, Supporting Steel Structure for Canal crossing / River Crossing / Water Way crossing and all related incidental works. Temporary road restoration shall be done by contractor. In the event of B.T cutting of PWD roads / major panchayath road junctions for road crossing, the pipe line trench shall be filled with GSB after an earth cushion of 0.3 m
Newly laid pipe lines shall be linked with the existing network using necessary Tees. Any M.S fabrication works required for linking with existing lines. is included in the scope of work. Supporting Steel bridge for Canal crossing / River Crossing / Water Way crossing shall be designed and constructed by the contractor.
|
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
1878100000
|
AS Number |
777 |
TS Amount (Rs) |
401500000 |
TS Number |
TS/2021-2022/2021/44403 and TS/2022-2023/2022/17630 |
Total Bill Submitted (Rs) |
73706885 |
Total Bill Paid (Rs) |
73706885 |
Population Benefitted |
30536 |
Capacity in MLD |
22.00 |
Actual Project Completion Date |
30 Jun 2024 |
Coverage |
Chalavara Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2021-22- Supplying, laying, Testing and commissioning of Distribution network and providing FHTCs ( 5412Nos) and road restoration works in Chalavara panchayath |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
120.642/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.90MM 10 KG LAYING WORK AT VEMBALATHUPADAM ON BLUECHIP CRUSHER ROAD. |
Palakkad Project Dn AE 4 |
|
08 May 2024 |
120.642/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.90MM 10 KG LAYING WORK AT VEMBALATHUPADAM ON BLUECHIP CRUSHER ROAD. |
Palakkad Project Dn AE 4 |
|
06 May 2024 |
120.481/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.CULVERT CROSSING WORK NEAR BLUECHIP CRUSHER AT VEMBALATHUPADAM ON VANIYAMKULAM VALLAPUZHA PWD ROAD |
Palakkad Project Dn AE 4 |
|
04 May 2024 |
119.805/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.IRISH BREAKING WORK AT KAYILAD ON VANIYAMKULAM VALLAPUZHA PWD ROAD |
Palakkad Project Dn AE 4 |
|
02 May 2024 |
119.805/190.905 km completed. Remaining HDPE & DI pipe laying work progressing, road restoration & house connection -3286/5412 progressing, total 3178 geo tagged ,FHTC-0.PWD road cutting Permission not issued. |
Palakkad Project Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/08/2022 |
Scheduled date of Completion of the Project |
25 Aug 2023 |
Expected date of Completion |
30/06/2024 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
25 Jan 2022 |