Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 2.0-Package 3-UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality

Project AMRUT 2.0-Package 3-UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality
Project Code IDKAMRUT112213858P3
Type Package
Main Project AMRUT 2.0 -UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality-General Civil Work
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 2.0-Package 3-UWSS Thodupuzha-Augmentation and Providing Functional Household Tap Connections to households in Thodupuzha Municipality
Status On-going
District Idukki
Executing Office Thodupuzha PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 23403000
TS Number 6878/2023-2024
Technical specification pipe line and FHTC in work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 22 Jun 2023

Approval Dates

NA 08 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thodupuzha PH Sub Dn AEE
Date: 30/12/2025

Work has been completed | 100% Completed

Work completed.

Thodupuzha PH Sn
Date: 29/08/2025

Work has been completed | 100% Completed

475 FHTC given , 475 nos FHTC Geotagged, Pipe laid 150 GI- 503.1 m , 90 PVC - 5457 m, 80 GI -2748 m, 160 PVC -1468.4, 40 GI- 2994.8m , Final bill submitted.