WSS to Kottiyoor, Kelakam and Kanichar panchayaths in Iritty Taluk of Kannur District - Phase I -Pckage-IVa

Project WSS to Kottiyoor, Kelakam and Kanichar panchayaths in Iritty Taluk of Kannur District - Phase I -Pckage-IVa
Project Code KNRNABARD12173151P4
Type Package
Main Project NABARD -RIDF-XXIII- WSS to Kottiyoor, Kelakam and Kanichar Panchayaths in Iritty Taluk of Kannur District - Phase I
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description construction of booster sump at Manjalapuram, CWPM from Kelakam Jn to Poovathinchola, sump at Poovathinchola, CWPM from Poovathinchola to Velloonni,GL tank at Velloonni, Supplying and erection of pumpsets.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No2
Agreement Number
Agreement Date
TS Amount (Rs) 61000000
TS Number 4/11/2020
Technical specification sump at Manjalapuram-3 lakh ltr capacity, CWPM from Kelakam Jn to Poovathinchola-300mm DI -1950m, sump at Poovathinchola-8 lakh ltr, CWPM from Poovathinchola to Velloonni-200mm DI-1160m, GL tank at Velloonni-4 lakh ltr ,Supplying and erection of pumpsets 1-At Manjalapuram sump 3 X 70 HP(for sump at Poovathinchola) 2 X 60 HP (for sump at Kambipalam) 2- At Kambipalam pump house 3 X 25 HP (sump at Memala) 2 X 5 HP(Existing OHSR at Parathode) 3 - At Poovathinchola 3 X 70 HP (At Velloonni)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 18 Aug 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 04 Nov 2020
Estimate Approval 04 Nov 2020
NIT Approval 01 Jan 2021
Tender Closing 14 Jun 2021
Technichal Pre-Qualification 17 Jun 2021
Price bid opening 17 Jun 2021

Approval Dates

Workorder Date 19 Nov 2021
NA 30 Nov 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Proj AE 2
Date: 27/08/2022

Work has started | 1% Completed

This work dropped. Estimate split up and work order issued..

Koothuparamba Proj AE 2
Date: 05/08/2022

Work in progress | 0% Completed

Estimate split up and re tendered and work order issued..