JJM – CWSS to Kunnathoor - WSS to Kulasekharapuram Panchayath in Karunagapally Taluk – Supplying and Laying various size distribution mains and providing FHTCs (10054) in Kulasekharapuram Grama Panchayath
Project |
JJM – CWSS to Kunnathoor - WSS to Kulasekharapuram Panchayath in Karunagapally Taluk – Supplying and Laying various size distribution mains and providing FHTCs (10054) in Kulasekharapuram Grama Panchayath |
Project Code |
KLMJJM092111836 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM – CWSS to Kunnathoor - WSS to Kulasekharapuram Panchayath in Karunagapally Taluk – Supplying and Laying various size distribution mains and providing FHTCs (10054) in Kulasekharapuram Grama Panchayath |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
234000000
|
AS Number |
G.O(R)No.489/2021/WRD |
TS Amount (Rs) |
234860000 |
TS Number |
TS no.19514/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
40500 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
01 Jun 2023 |
Coverage |
Supplying and Laying various size distribution mains and providing FHTCs (10054) in Kulasekharapuram Grama Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM – CWSS to Kunnathoor - WSS to Kulasekharapuram Panchayath in Karunagapally Taluk – Supplying and Laying various size distribution mains and providing FHTCs (10054) in Kulasekharapuram Grama Panchayath |
Oachira PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
Providing FHTC ongoing. Completed FHTC 773 Nos., HTC 463 Nos |
Oachira AE |
|
21 Jun 2024 |
Providing FHTC ongoing. Completed FHTC 773 Nos., HTC 463 Nos |
Oachira AE |
|
18 Jun 2024 |
Providing FHTC ongoing. Completed FHTC 773 Nos., HTC 463 Nos |
Oachira AE |
|
12 Jun 2024 |
Providing FHTC ongoing. Completed FHTC 773 Nos., HTC 463 Nos |
Oachira AE |
|
10 Jun 2024 |
Providing FHTC ongoing. Completed FHTC 773 Nos., HTC 458 Nos |
Oachira AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/06/2022 |
Scheduled date of Completion of the Project |
01 Jun 2023 |
Expected date of Completion |
24/07/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
05 Feb 2022 |