JJM - Parassala Panchyath -Design, Supplying, Laying Testing &commissioning of of 300 mm DI K9 From WTP site at Ponvilla to Idichakaplamoodu and Interconnection works

Project JJM - Parassala Panchyath -Design, Supplying, Laying Testing &commissioning of of 300 mm DI K9 From WTP site at Ponvilla to Idichakaplamoodu and Interconnection works
Project Code TVMJJM08209516P1
Type Package
Main Project JJM - Parassala Panchyath -Design, Supplying, Laying Testing &commissioning of of 300 mm DI K9 From WTP site at Ponvilla to Idichakaplamoodu and Interconnection works
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Work includes interconnecting the aleady existing 500 mm DI (Kaalippara Scheme) with 200 mm DI at Idichakkaplamoodu
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 9570000
TS Number TS/2021-2022/2022/6305
Technical specification Work includes interconnecting the aleady existing 500 mm DI with 200 mm DI using 200 mm & 300 mm DI pipes

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/03/2022
Scheduled date of Completion as per agreement 18 Apr 2022
Expected date of Completion 18/04/2022

Processing Dates

TS Date 22 Feb 2022
Estimate Approval 22 Feb 2022

Approval Dates

Workorder Date 05 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thiruvananthapuram Project AE2
Date: 11/09/2022

Work has been completed | 100% Completed

Work completed.

Thiruvananthapuram Project AE2
Date: 10/09/2022

Work has been completed | 100% Completed

Work completed.