Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District

Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
Project Code MLPJJM092110135
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description CWSS to Thazhekkode & Alipparamba Panchayaths- Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21. 2. Package II - Design Construction of OHSR, GLSR and supplying and laying of Gravity mains. 3. Package III - Distribution system to Thazhekkode and Alipparamba Panchayath
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 11800000000
AS Number G.O Rt No.489/2021/WRD Dated 18-09-2021
TS Amount (Rs) 11679000000
TS Number 15032/20-21
Total Bill Submitted (Rs) 286492604
Total Bill Paid (Rs) 286492604
Population Benefitted 83937
Capacity in MLD 12.00
Actual Project Completion Date 08 Sep 2023
Coverage Thazhekkode and Alipparamba panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba -Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21.Panchayath in Malappuram District Project Division Malappuram
2 Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. Panchayath in Malappuram District Project Division Malappuram
3 Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package III - Survey , design , supplying and laying of distribution system to Thazhekkode and Alipparamba Panchayath. Project Division Malappuram
4 JJM -CWSS to Thazhekkode Alipparamba pt-Additional pipeline extension,Providing FHTC & road restoration for NH,PWD &LSGD - Package 1,2&3 Re-Appropriation Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 May 2023 Package 1-pipe line work along PWD road SH 53 completed ,Cherukara road Manalaya road up to 2 km both side completed, GLSR completed - Pipe line and FHTC work progressing 2100 nos completed ,MS work on culvert completed, Plastering on GLSR out side completed inside Water proofing work,painting of outside surface of tank compleated, geotaging HTC in progress Package ll-OHSR @ Bidavumala up to roof slab concert compleated plastering started OHSR @ Kainassarykotta footing concreet compleated,plinth beam concret compleated, first brace concert compleated,columns up to floor beam compleated, floor beam concret compleated @Vellappara GLSR Earth work compleated.pipe supplied. Clear water Pumping main 500 mm DI pipe laying in progress-2100 mtr completed Package lll-Pipe line in Thazhekkode and Alipparamba panchayath progressing-159km compleated .. 1400HTC compleated,geotaging work also in progress Malappuram Project Dn
10 Mar 2023 Package I - GLSR completed - Pipeline Along PWD road compleated , FHTC work progressing 2.Package II - pipe supplied 500 mm DI pumping main laying in progress . Vidavumala 7 LL OHSR up tofloor beam concret compleated ,Kainassry kotta earth work compleated PCC Compleated, plinth beam concret compleatedVellappara GLSR earth work compleated3.Package III - Design of net work approved-Pipes supply started laying progressing along panchayath roads in Thazhekkode and Alipparamab Pts- 100 km compleated HTC also in progress-400 nos compleated Malappuram Project Dn
02 Mar 2023 Package I - GLSR completed - Pipeline Along PWD road compleated , FHTC work progressing 2.Package II - pipe supplied 500 mm DI pumping main laying in progress . Vidavumala 7 LL OHSR up tofloor beam concret compleated ,Kainassry kotta earth work compleated PCC Compleated, plinth beam in progress Vellappara GLSR earth work compleated3.Package III - Design of net work approved-Pipes supply started laying progressing along panchayath roads in Thazhekkode and Alipparamab Pts FHTC also in progress Malappuram Project Dn
22 Feb 2023 Package I - GLSR completed - Pipeline Along PWD road compleated , FHTC work progressing 2.Package II - Supply order placed for pipes . Vidavumala 7 LL OHSR column footting,Concreet upto plinth beam compleated ,Kainassry kotta earth work compleated PCC Compleated Fotting concreet in progress3.Package III - Design of net work approved-Pipes supply started laying progressing along panchayath roads in Thazhekkode and Alipparamab Pts FHTC also in progress Malappuram Project Dn
15 Feb 2023 Package I - GLSR completed - Pipeline Along PWD road compleated , FHTC work progressing 2.Package II - Supply order placed for pipes . Vidavumala 7 LL OHSR column footting,Concreet upto plinth beam compleated ,Kainassry kotta earth work compleated PCC Compleated Fotting concreet in progress3.Package III - Design of net work approved-Pipes supply started laying progressing along panchayath roads in Thazhekkode and Alipparamab Pts FHTC also in progress Malappuram Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/04/2022
Scheduled date of Completion of the Project 30 Sep 2023
Expected date of Completion 31/12/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 08 Dec 2021

Other details

Project Officers View