JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy

Project JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM08204326
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 15590000
AS Number GO(RT )NO 541/2020/WRD DATED 21/08/2020
TS Amount (Rs) 15590000
TS Number TS/2020-2021/2020/16420 DATED 25/08/2020
Total Bill Submitted (Rs) 11038000
Total Bill Paid (Rs) 11038000
Population Benefitted 7070
Capacity in MLD 45.00
Actual Project Completion Date 30 Apr 2022
Coverage Population covered - 7070
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)--2020-21-Phase I-(Balance work )--Thalayazham Panchayath - Replacement of old 180HP No:2 centrifugal pumpsets at old Clear Water Pumphouse,Mevelloor. T V Puram
2 JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy T V Puram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Oct 2022 WORK COMPLETED Kaduthuruthy Dn EE
28 Sep 2022 WORK COMPLETED Kaduthuruthy Dn EE
27 Sep 2022 WORK COMPLETED Kaduthuruthy Dn EE
26 Sep 2022 WORK COMPLETED Kaduthuruthy Dn EE
20 Sep 2022 WORK COMPLETED Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/11/2020
Scheduled date of Completion of the Project 30 Oct 2021
Expected date of Completion 31/05/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 25 Aug 2020

Other details

Project Officers View