- Home
- JJM-2020-21-Thalayazham Panchayath - Pro...
JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project |
JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy |
Project Code |
KTMJJM08204326 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kaduthuruthy PH Dn |
AS Amount (Rs) |
15590000
|
AS Number |
GO(RT )NO 541/2020/WRD DATED 21/08/2020 |
TS Amount (Rs) |
15590000 |
TS Number |
TS/2020-2021/2020/16420 DATED 25/08/2020 |
Total Bill Submitted (Rs) |
11038000 |
Total Bill Paid (Rs) |
11038000 |
Population Benefitted |
7070 |
Capacity in MLD |
45.00 |
Actual Project Completion Date |
30 Apr 2022 |
Coverage |
Population covered - 7070 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)--2020-21-Phase I-(Balance work )--Thalayazham Panchayath - Replacement of old 180HP No:2 centrifugal pumpsets at old Clear Water Pumphouse,Mevelloor. |
T V Puram |
|
2 |
JJM-2020-21-Thalayazham Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy |
T V Puram |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Oct 2022 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
28 Sep 2022 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
27 Sep 2022 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
26 Sep 2022 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
20 Sep 2022 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/11/2020 |
Scheduled date of Completion of the Project |
30 Oct 2021 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
25 Aug 2020 |