JJM PHASE II (2021-22) WSS to Manathavady, Edavaka and Naloornadu villages - Providing Functional Household Tap Connections in EDAVAKA Grama Panchayath

Project JJM PHASE II (2021-22) WSS to Manathavady, Edavaka and Naloornadu villages - Providing Functional Household Tap Connections in EDAVAKA Grama Panchayath
Project Code WYDJJM09218481P1
Type Package
Main Project JJM PHASE II (2021-22) WSS to Manathavady, Edavaka and Naloornadu villages - Providing Functional Household Tap Connections in EDAVAKA Grama Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Functional Household Tap Connections (4000 FHTC) in Edavakka Grama Panchayath in Wayanad District
Status On-going
District Wayanad
Executing Office Mananthavady PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 278000000
TS Number TS/2021-2022/2021/36615
Technical specification JJM(2021-22) - Phase II - WSS to Manathavady, Edavaka and Naloornadu villages - Providing Functional Household Tap Connections (4000 FHTC) in Edavakka Grama Panchayath in Wayanad District
Contractor M Abdul Nazer (Mob: 9446260421)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/02/2022
Scheduled date of Completion as per agreement 31 Mar 2024
Expected date of Completion 30/06/2024

Processing Dates

TS Date 07 Dec 2021
Estimate Approval 07 Dec 2021
NIT Approval 07 Dec 2021
Tender Closing 31 Dec 2021
Technichal Pre-Qualification 03 Jan 2022
Price bid opening 03 Jan 2022

Approval Dates

Workorder Date 04 Feb 2022
NA 11 Feb 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mananthavady PH Sn - AE
Date: 29/06/2024

Work in progress | 93% Completed

House Connection works at Dwaraka and 4th mile area.

Mananthavady PH Sn - AE
Date: 24/06/2024

Work in progress | 93% Completed

63mm pipe laying at peechangode branch road.