DEPOSITCFC Tide Fund -Renovation and conservation of Maruthady Kattakkal Kayal in Sakthikulangara Village in Chavara Constituency. Replacement of existing Pipeline work-Balance work of temporary arrangements-Pipeline Work

Project DEPOSITCFC Tide Fund -Renovation and conservation of Maruthady Kattakkal Kayal in Sakthikulangara Village in Chavara Constituency. Replacement of existing Pipeline work-Balance work of temporary arrangements-Pipeline Work
Project Code KLMDEPO102416809
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-CFC Tide Fund -Renovation and conservation of Maruthady Kattakkal Kayal in Sakthikulangara Village in Chavara Constituency. Replacement of existing Pipeline work-Balance work of temporary arrangements-Pipeline Work
Status Completed
District Kollam
Executing Office Kollam WS Sn 2
AS Amount (Rs) 100000
AS Number A8-5642018
TS Amount (Rs) 100000
TS Number 17230/2024-2025
Total Bill Submitted (Rs) 73412
Total Bill Paid (Rs) 0
Population Benefitted 5600
Capacity in MLD 2.00
Actual Project Completion Date 03 Dec 2024
Coverage Dn-1 Maruthady Dn full coverage and Dn -2 (P)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSITCFC Tide Fund Kollam WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2025 WORK COMPLETED ON 03/12/2024 AND FINAL BILL SUBMITTED Kollam WS Sn 2 - AE
06 Jan 2025 Work started on 2/12/2024 and progressing (pipe laying completed) Kollam WS Sn 2 - AE
01 Jan 2025 Work started on 2/12/2024 and progressing (pipe laying completed) Kollam WS Sn 2 - AE
26 Dec 2024 Work started on 2/12/2024 and progressing (pipe laying completed) Kollam WS Sn 2 - AE
23 Dec 2024 Work started on 2/12/2024 and progressing (pipe laying completed) Kollam WS Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/10/2024
Scheduled date of Completion of the Project 05 Dec 2024
Expected date of Completion 30/11/2024

Processing Dates

AS Date 15 Oct 2024
TS Date 28 Oct 2024

Other details

Project Officers View