- Home
- 09-Imrpovement-UWSS to Thodupuzha- Impro...
09-Imrpovement-UWSS to Thodupuzha- Improving distribution network in various roads of Thodupuzha Municipality - Northern Part.
| Project |
09-Imrpovement-UWSS to Thodupuzha- Improving distribution network in various roads of Thodupuzha Municipality - Northern Part. |
| Project Code |
IDKGOK03182335 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
UWSS to Thodupuzha:-Improving distribution network in various roads of Thodupuzha Municipality - Northern Part. |
| Status |
Completed |
| District |
Idukki |
| Executing Office |
Thodupuzha PH Dn |
| AS Amount (Rs) |
1500000
|
| AS Number |
|
| TS Amount (Rs) |
|
| TS Number |
|
| Total Bill Submitted (Rs) |
1500312 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
18 Aug 2018 |
| Coverage |
Thodupuzha Muncipality |
Packages
| No. |
Project Name |
Location |
View |
| No Packages has been added for this project. |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 17 Nov 2020 |
completed |
Thodupuzha PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
18/08/2017 |
| Scheduled date of Completion of the Project |
Date is not specified |
| Expected date of Completion |
18/08/2017 |
Processing Dates
| AS Date |
29 Mar 2016 |
| TS Date |
23 Mar 2017 |
Approval Dates
| Workorder Date |
03 Apr 2017 |
| NA |
21 Apr 2017 |