Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath

Project Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath
Project Code EKMJJM08203266P1
Type Package
Main Project Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Multi Village Scheme - RWSS to Karukutty and Mookkannoor Panchayaths - Replacement of 315 mm PVC pipe to 300 mm DI K9 pipe, Extension of pipe line, Providing FHTC and allied works in Karukutty Panchayath
Status On-going
District Ernakulam
Executing Office Angamaly Sn
Agreement Number
Agreement Date
TS Amount (Rs) 247000000
TS Number TS/2020-2021/2020/13573
Technical specification 6411 FHTC,300mm DI pipe ,110mm PVC pipe and 90mm PVC pipe including renovation of Pumphouse.
Contractor M V VISWANATHAN (Mob: 9447079850)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/02/2021
Scheduled date of Completion as per agreement 30 Jun 2021
Expected date of Completion 30/11/2022

Processing Dates

TS Date 23 Sep 2020
Estimate Approval 23 Sep 2020
NIT Approval 23 Sep 2020
Tender Closing 21 Oct 2020
Price bid opening 09 Nov 2020

Approval Dates

Workorder Date 01 Jan 2021
NA 11 Feb 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Aluva AE JJM
Date: 19/04/2023

Work in progress | 68% Completed

Work preclosed vide proceedings no. PHC/CHN/JJM/13573/2020 Vol -II dated 03.04.2023 .

Aluva AE JJM
Date: 17/04/2023

Work in progress | 68% Completed