Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Construction of well cum pump house.

Project Construction of well cum pump house.
Project Code IDKGOI0302531P1
Type Package
Main Project ARP-CARWSS TO VELLATHOOVAL AND KONNATHADY VILLAGES
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description Construction of 6m dia well cum pump house.
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Construction of 6m dia RCC open well cum pump house.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/01/2010
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/01/2010

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana Project Dn EE
Date: 10/07/2021

Work has been completed | 100% Completed

Work Completed.

Kattappana Project Dn EE
Date: 31/01/2010

Work has been completed | 100% Completed

Construction Completed.