| Project | JalJeevam Mission- Phase II -BAWSS to Kundara and panchayths-Providing house connections from pipe line extension and replacement of pipes and part of rennovation of WTP (Elampal) in Ezhukone grama panchayat |
|---|---|
| Project Code | KLMJJM08204216P1 |
| Type | Package |
| Main Project | JalJeevam Mission- Phase II -BAWSS to Kundara and panchayths-Providing house connections from pipe line extension and replacement of pipes and part of rennovation of WTP (Elampal) in Ezhukone grama panchayat |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | JalJeevam Mission- Phase II -BAWSS to Kundara and panchayths-Providing house connections from pipe line extension and replacement of pipes and part of rennovation of WTP (Elampal) in Ezhukone grama panchayat |
| Status | On-going |
| District | Kollam |
| Executing Office | Kottarakkara PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 106900000 |
| TS Number | TS/2020-21/2020/20284 |
| Technical specification | Rennovation of plant and Replacement work |
| Contractor | M/s SURYA INTERNATIONAL ENTERPRISE PVT LTD (Mob: 9439525334) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 29/07/2021 |
|---|---|
| Scheduled date of Completion as per agreement | 23 Oct 2021 |
| Expected date of Completion | 30/06/2022 |
| TS Date | 25 Sep 2020 |
|---|---|
| Estimate Approval | 25 Sep 2020 |
| NIT Approval | 25 Sep 2020 |
| Tender Closing | 31 Dec 2020 |
| Technichal Pre-Qualification | 04 Jan 2021 |
| Price bid opening | 04 Jan 2021 |
| Workorder Date | 18 Feb 2021 |
|---|---|
| NA | 27 Apr 2021 |
| Kottarakkara PH Sn - AE |
| Date: 16/04/2026 |
Work in progress | 60% Completed
work temporary stopped.
| Kottarakkara PH Sn - AE |
| Date: 10/02/2026 |
Work in progress | 60% Completed
work stopped.