Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.

Project JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.
Project Code KNRJJM08302937
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 4762 Nos FHTC in Kadirur Panchayath
Status Completed
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 109209000
AS Number GO(Rt.No.541/2020/WRD Dated 21/8/2020
TS Amount (Rs) 789746000
TS Number 3520
Total Bill Submitted (Rs) 32886000
Total Bill Paid (Rs) 32886000
Population Benefitted 21000
Capacity in MLD 30.00
Actual Project Completion Date 22 Dec 2023
Coverage Population Benefitted---21000
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)- WSS to Anjarakandy Peralassery and Adjoining Panchayaths-Laying distribution and providing FHTC in Kadirur Panchayath- Balance Work -Pipeline Work. Perlassery Sn 1
2 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassd and adjoining panchayaths-Phase II.(Chundangapoil area) Perlassery Sn 1
3 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassd and adjoining panchayaths-Phase II.(Ponniam area) Perlassery Sn 1
4 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassd and adjoining panchayaths-Phase II. Zone-II (Sarambi - Choyyadam area)-Laying distribution system and providing FHTCs. Perlassery Sn 1
5 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.(Kakkara and adjoining area) Perlassery Sn 1
6 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.(Kunduchira area) Perlassery Sn 1
7 JJM- Kannur District-Kadirur Panchayath-WSS to Anjarakandy Peralassery and adjoining panchayaths-Phase II.(Pulliyod and adjoining area) Perlassery Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Completed Perlasserry Sn 1
01 Jan 2024 Work in progress Perlasserry Sn 1
08 Dec 2023 work in progress Perlasserry Sn 1
05 Dec 2023 work in progress Perlasserry Sn 1
30 Nov 2023 Work in progress Perlasserry Sn 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/09/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 04 Nov 2020

Other details

Project Officers View