Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat.
Project Code
KLMJJM082015243
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat.
Status
On-going
District
Kollam
Executing Office
Kollam PH Dn
AS Amount (Rs)
2130000000
AS Number
Go(Rt) No.541/2020/WRD
TS Amount (Rs)
22980000
TS Number
3923/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat
Sasthamcottah WS Sn2
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
16 May 2024
The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level
Sasthamcotta WS Sn 2 HW - AE
13 May 2024
The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level
Sasthamcotta WS Sn 2 HW - AE
09 May 2024
The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level
Sasthamcotta WS Sn 2 HW - AE
06 May 2024
The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level
Sasthamcotta WS Sn 2 HW - AE
03 May 2024
The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level