Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat.

Project Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat.
Project Code KLMJJM082015243
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat.
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 2130000000
AS Number Go(Rt) No.541/2020/WRD
TS Amount (Rs) 22980000
TS Number 3923/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jala Jeevan Mission Mynagappally : Package II- Reconcreating of Panchayat road and reconstruction of PWD roads in Mynagappally Grama Panchayat Sasthamcottah WS Sn2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level Sasthamcotta WS Sn 2 HW - AE
13 May 2024 The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level Sasthamcotta WS Sn 2 HW - AE
09 May 2024 The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level Sasthamcotta WS Sn 2 HW - AE
06 May 2024 The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level Sasthamcotta WS Sn 2 HW - AE
03 May 2024 The contractor has executed only 12% of work .There after no progress in work.The time of completion of the work was expired on 31.12.2023 .The request for extension of time of completion has not been submitted by the contractor till date inspite of several intimations. So this work recommended for arranging by the risk& cost of the contractor .Report with revised estimate also submitted to higher level Sasthamcotta WS Sn 2 HW - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/10/2022
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 26/05/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 17 May 2022