Jal Jeevan Mission (JJM)-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath

Project Jal Jeevan Mission (JJM)-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath
Project Code KNRJJM08203000P6
Type Package
Main Project Jal Jeevan Mission-Kannur district-Kurumathur Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JaLaying Distribution line &Providing FHTCs (Balance Portion) in Kurumathur Panchayath
Status On-going
District Kannur
Executing Office Thaliparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 71800000
TS Number WRD/KWA-CE(NR)/EST TS/12674/2022 26 1 1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/10/2023
Scheduled date of Completion as per agreement 03 Apr 2024
Expected date of Completion 31/12/2023

Processing Dates

TS Date 08 May 2023
Estimate Approval 08 May 2023
NIT Approval 08 May 2023
Tender Closing 02 Jun 2023
Technichal Pre-Qualification 03 Jun 2023
Price bid opening 03 Jun 2023

Approval Dates

Workorder Date 16 Aug 2023
NA 26 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Section
Date: 25/06/2024

Work in progress | 50% Completed

Work in progress 15km pipe laying & 470 FHTCs given.

Thaliparamba WS Section
Date: 13/06/2024

Work in progress | 50% Completed

Work in progress 15km pipe laying & 450 FHTCs given.