Project | Jal Jeevan Mission (JJM)-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath-Laying Distribution line &Providing FHTCs (Balance Portion in Kurumathur Panchayath |
---|---|
Project Code | KNRJJM08203000P6 |
Type | Package |
Main Project | Jal Jeevan Mission-Kannur district-Kurumathur Panchayath- JICA WSS to Pattuvam and Adjoining villages Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JaLaying Distribution line &Providing FHTCs (Balance Portion) in Kurumathur Panchayath |
Status | On-going |
District | Kannur |
Executing Office | Thaliparamba WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 71800000 |
TS Number | WRD/KWA-CE(NR)/EST TS/12674/2022 26 1 1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 03 Apr 2024 |
Expected date of Completion | 31/12/2023 |
TS Date | 08 May 2023 |
---|---|
Estimate Approval | 08 May 2023 |
NIT Approval | 08 May 2023 |
Tender Closing | 02 Jun 2023 |
Technichal Pre-Qualification | 03 Jun 2023 |
Price bid opening | 03 Jun 2023 |
Workorder Date | 16 Aug 2023 |
---|---|
NA | 26 Sep 2023 |
Thaliparamba WS Section |
Date: 25/06/2024 |
Work in progress | 50% Completed
Work in progress 15km pipe laying & 470 FHTCs given.
Thaliparamba WS Section |
Date: 13/06/2024 |
Work in progress | 50% Completed
Work in progress 15km pipe laying & 450 FHTCs given.