Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 6,7,8,9-Pipeline Work

Project Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 6,7,8,9-Pipeline Work
Project Code KLMJJM102316951P1
Type Package
Main Project Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 6,7,8,9-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Alayamon Panchayath re appropriation-WARD 6,7,8,9-Pipeline Work
Status On-going
District Kollam
Executing Office Madathara Sn
Agreement Number
Agreement Date
TS Amount (Rs) 6834900
TS Number WRD/KWA-CE(SR)/EST_TS/3321/2024_26_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/10/2025

Processing Dates

TS Date 24 Feb 2024
Estimate Approval 22 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Madathara PH Sn - AE
Date: 31/10/2025

Work has been completed | 100% Completed

work completed satisfactory.

Madathara PH Sn - AE
Date: 23/09/2025

Work in progress | 91% Completed

ongoing.