Project | JJM 2020-21 Providing FHTC's to House holds through pipe line extension in various wards of venganoor Grama panchayath (phase 2) |
---|---|
Project Code | TVMJJM08205567P1 |
Type | Package |
Main Project | JJM 2020-21 Providing FHTC's to House holds thrrough pipe line extension in various wards of Venganoor Grama panchayath(Phase II) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM 2020-21 Providing FHTC's to House holds through pipe line extension in various wards of venganoor Grama panchayath (phase 2) |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Aralummoodu WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 82500000 |
TS Number | TS/2020-2021/2020/19060 |
Technical specification | Providing 3000 FHTCs to House holds through pipe line extension in various wards of venganoor Grama panchayath |
Contractor | Sri. Suraj. R (Mob: 9605883360) |
Review Date | Review Message | Review Attended By |
---|---|---|
28 May 2021 | The work is affected by covid-19 and it is expected to be resumed on 01.06.2021 | Executive Engineer |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
31 Dec 2021 | Pending | Pending | Contract Related Risks | Time of completion is over | No comments available. | Pending |
15 Nov 2021 | Pending | Pending | Natural Calamities Related | Due to heavy rainfall and flood the work has not been done from last three days. | No comments available. | Pending |
28 Sep 2021 | Pending | Pending | Road Cut Related Risk | PWD & NH Cutting | No comments available. | Pending |
09 Jun 2021 | Pending | Pending | Road Cut Related Risk | PWD & NH Cutting | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 25 Aug 2021 |
Expected date of Completion | 30/04/2022 |
TS Date | 05 Sep 2020 |
---|---|
Estimate Approval | 05 Sep 2020 |
NIT Approval | 05 Sep 2020 |
Tender Closing | 04 Sep 2020 |
Technichal Pre-Qualification | 07 Sep 2020 |
Price bid opening | 07 Sep 2020 |
Workorder Date | 26 Feb 2021 |
---|---|
NA | 06 Mar 2021 |
Aralumoodu AE |
Date: 15/07/2022 |
Work has been completed | 100% Completed
Final bill submitted.
Aralumoodu AE |
Date: 14/07/2022 |
Work has been completed | 100% Completed
Final bill submitted.