WRD009-02 -KIIFB- WSS to Mattanur and Iritty Phase II -Laying Distribution System

Project WRD009-02 -KIIFB- WSS to Mattanur and Iritty Phase II -Laying Distribution System
Project Code KNRKIIFB042315543
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description WSS to Mattannur & Iritty Municipalities -Phase II- Laying Distribution system and providing FHTCs in Mattannur & Iritty Municipalities
Status On-going
District Kannur
Executing Office Mattannur Project Dn
AS Amount (Rs) 2697000000
AS Number WRD009-02/APR-6/2023/KIIFB
TS Amount (Rs) 2571200000
TS Number WRD/KWA-CE(NR)/EST_TS/21311/2023_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 417320
Capacity in MLD 42.00
Actual Project Completion Date Date is not specified
Coverage Entire area of Mattannur & Iritty Municipalities

Packages

No. Project Name Location View
1 WRD 009-02 -KIIFB-WSS to Mattannur & Iritty Municipalities-Phase II-Laying Distribution system and providing FHTCs inIritty Municipality Mattannur Project Dn
2 WRD 009-02 -KIIFB-WSS to Mattannur & Iritty Municipalities-Phase II-Laying Distribution system and providing FHTCs in Mattannur Municipality Mattannur Project Dn

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2024
Scheduled date of Completion of the Project 31 Mar 2025
Expected date of Completion 31/03/2025

Processing Dates

AS Date 25 Apr 2023
TS Date 27 Oct 2023

Other details

Project Officers View