- Home
- WRD009-02 -KIIFB- WSS to Mattanur and Ir...
WRD009-02 -KIIFB- WSS to Mattanur and Iritty Phase II -Laying Distribution System
Project |
WRD009-02 -KIIFB- WSS to Mattanur and Iritty Phase II -Laying Distribution System |
Project Code |
KNRKIIFB042315543 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
WSS to Mattannur & Iritty Municipalities -Phase II- Laying Distribution system and providing FHTCs in Mattannur & Iritty Municipalities |
Status |
On-going |
District |
Kannur |
Executing Office |
Mattannur Project Dn |
AS Amount (Rs) |
2697000000
|
AS Number |
WRD009-02/APR-6/2023/KIIFB |
TS Amount (Rs) |
2571200000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/21311/2023_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
417320 |
Capacity in MLD |
42.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Entire area of Mattannur & Iritty Municipalities |
Packages
No. |
Project Name |
Location |
View |
1 |
WRD 009-02 -KIIFB-WSS to Mattannur & Iritty Municipalities-Phase II-Laying Distribution system and providing FHTCs inIritty Municipality |
Mattannur Project Dn |
|
2 |
WRD 009-02 -KIIFB-WSS to Mattannur & Iritty Municipalities-Phase II-Laying Distribution system and providing FHTCs in Mattannur Municipality |
Mattannur Project Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/03/2024 |
Scheduled date of Completion of the Project |
31 Mar 2025 |
Expected date of Completion |
31/03/2025 |
Processing Dates
AS Date |
25 Apr 2023 |
TS Date |
27 Oct 2023 |