Budget Proposal -2020-2021 UWSS to Nedumangadu Supply ,erection ,commissioning of pumps at various pump houses in Nedumangadu Muncipality and over hauling and oil filtration of 500KVA Transformer at Kalathara.
| Project |
Budget Proposal -2020-2021 UWSS to Nedumangadu Supply ,erection ,commissioning of pumps at various pump houses in Nedumangadu Muncipality and over hauling and oil filtration of 500KVA Transformer at Kalathara. |
| Project Code |
TVMGOK12218640P2 |
| Type |
Package |
| Main Project |
Budget Proposal 2021-22 -UWSS to Nedumangad-Augmentation and Improvement of water supply to Nedumangad
|
| Funding Agency |
GOK |
| Category |
Urban Water Supply Schemes – Rehabilitation |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
Budget Proposal -2020-2021 UWSS to Nedumangadu Supply ,erection ,commissioning of pumps at various pump houses in Nedumangadu Muncipality and over hauling and oil filtration of 500KVA Transformer at Kalathara. |
| Status |
On-going |
| District |
Thiruvananthapuram |
| Executing Office |
Nedumangad WW Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
9529965 |
| TS Number |
17652 |
| Technical specification |
Budget Proposal -2020-2021 UWSS to Nedumangadu Supply ,erection ,commissioning of pumps at various pump houses in Nedumangadu Muncipality and over hauling and oil filtration of 500KVA Transformer at Kalathara |
| Contractor |
M/S Royal Electricals (Mob: 9942222443) |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
03/05/2022 |
| Scheduled date of Completion as per agreement |
06 Jun 2022 |
| Expected date of Completion |
31/12/2022 |
Processing Dates
| TS Date |
11 Jan 2022 |
| Estimate Approval |
11 Jan 2022 |
| NIT Approval |
11 Jan 2022 |
| Tender Closing |
24 Jan 2022 |
| Technichal Pre-Qualification |
27 Jan 2022 |
| Price bid opening |
27 Jan 2022 |
Approval Dates
| Workorder Date |
22 Feb 2022 |
| NA |
04 Mar 2022 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Nedumangad AE |
| Date: 10/04/2026 |
Work in progress | 50% Completed
pump installed at Kalatthara, Sheemamula, and Uzhappakonnam.
| Nedumangad AE |
| Date: 31/01/2026 |
Work in progress | 50% Completed
pump installed at Kalatthara, Sheemamula, and Uzhappakonnam
.