Project | JJM WSS to Cheekode and Adjoining Villages- Providing FHTC toVazhayur Panchayath. |
---|---|
Project Code | MLPJJM08202868 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM WSS to Cheekode and Adjoining Villages- Providing 6746 FHTC toVazhayur Panchayath |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
AS Amount (Rs) | 326050000 |
AS Number | G.O.(Rt)No.897/2023/WRD |
TS Amount (Rs) | 281800000 |
TS Number | TS/2020/20658 |
Total Bill Submitted (Rs) | 123700365 |
Total Bill Paid (Rs) | 100 |
Population Benefitted | 36909 |
Capacity in MLD | 41.00 |
Actual Project Completion Date | 16 Dec 2021 |
Coverage | Full Coverage |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 May 2024 | New work tender under process | Malapuram Proj Dn AE 4 | |
14 Feb 2024 | New work tender under process | Malapuram Proj Dn AE 4 | |
24 May 2023 | maintenance work is on going | Malapuram Proj Dn AE 4 | |
11 May 2023 | Interconnection work and road restoration work in progress at various wards | Malapuram Proj Dn AE 4 | |
05 May 2023 | Interconnection work and road restoration work in progress at various wards | Malapuram Proj Dn AE 4 |
Date of start of Project | 01/01/2021 |
---|---|
Scheduled date of Completion of the Project | 16 Dec 2021 |
Expected date of Completion | 31/01/2023 |
AS Date | 26 Oct 2023 |
---|---|
TS Date | 17 Dec 2023 |
Project Officers | View |
---|