Project | Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III |
---|---|
Project Code | TCRJJM022213936P3 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-5th SLSSC -Water Supply Scheme to Mulamkunnathukavu Grama Panchayath in Thrissur District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III |
Status | On-going |
District | Thrissur |
Executing Office | Thrissur WW Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 155070000 |
TS Number | WRD/KWA-CE(CR)EST_TS/2120/2022_26_1_1 |
Technical specification | Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III |
Contractor | OMDHAR ENGINEERING PVT.LTD. (Mob: 7337442967) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 08 Mar 2024 |
Expected date of Completion | 31/07/2024 |
TS Date | 19 Sep 2022 |
---|---|
Estimate Approval | 19 Sep 2022 |
NIT Approval | 19 Sep 2022 |
Tender Closing | 14 Dec 2022 |
Technichal Pre-Qualification | 14 Dec 2022 |
Price bid opening | 16 Dec 2022 |
Workorder Date | 08 Mar 2023 |
---|---|
NA | 25 Mar 2023 |
Thrissur WW Sn - AE 1 |
Date: 28/06/2024 |
Work in progress | 8% Completed
Laying Connection work in progress. HTCs given. Second part bill submitted..
Thrissur WW Sn - AE 1 |
Date: 25/06/2024 |
Work in progress | 8% Completed
Laying Connection work in progress. HTCs given. Second part bill submitted..