Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III

Project Jal Jeevan Mission(JJM)-5th SLSSC - Water Supply Scheme to Mulamkunnthukavu Grama Panchayath in Thrissur District-Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III
Project Code TCRJJM022213936P3
Type Package
Main Project Jal Jeevan Mission (JJM)-5th SLSSC -Water Supply Scheme to Mulamkunnathukavu Grama Panchayath in Thrissur District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III
Status On-going
District Thrissur
Executing Office Thrissur WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 155070000
TS Number WRD/KWA-CE(CR)EST_TS/2120/2022_26_1_1
Technical specification Providing and laying Distribution lines and 3406 FHTCs to Mulamkunnathukavu Zone-Package III
Contractor OMDHAR ENGINEERING PVT.LTD. (Mob: 7337442967)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/03/2023
Scheduled date of Completion as per agreement 08 Mar 2024
Expected date of Completion 31/07/2024

Processing Dates

TS Date 19 Sep 2022
Estimate Approval 19 Sep 2022
NIT Approval 19 Sep 2022
Tender Closing 14 Dec 2022
Technichal Pre-Qualification 14 Dec 2022
Price bid opening 16 Dec 2022

Approval Dates

Workorder Date 08 Mar 2023
NA 25 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur WW Sn - AE 1
Date: 28/06/2024

Work in progress | 8% Completed

Laying Connection work in progress. HTCs given. Second part bill submitted..

Thrissur WW Sn - AE 1
Date: 25/06/2024

Work in progress | 8% Completed

Laying Connection work in progress. HTCs given. Second part bill submitted..