JJM - Phase III - Improvements of CARWSS to Moorkkanad and adjoining Panchayaths

Project JJM - Phase III - Improvements of CARWSS to Moorkkanad and adjoining Panchayaths
Project Code MLPJJM022212048
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Improvements of existing scheme
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 2069000000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 1520000000
TS Number 7906,9878,9728,10603,11540,11541,11539/22-23
Total Bill Submitted (Rs) 221640761
Total Bill Paid (Rs) 221640761
Population Benefitted 234364
Capacity in MLD 43.00
Actual Project Completion Date 23 Feb 2022
Coverage Moorkkanad, Kuruva, Puzhakkattiri,Makkaraparamba, Kootilangadi,Mankada Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal Jeevan Mission- 21-22-CARWSS to Moorkanad and adjoining Villages-Improvements of CARWSS to Moorkkand and Adjoining Panchayaths - Enhancing the Existing distribution line and Laying distribution line to non covered area and providing FHTCs in Kurva Panchayath.--Pipeline Work Project Division Malappuram
2 JJM -Improvements of CARWSS to Moorkkanad and Adjoining Panchayaths -Package VII Supplying and laying of Distribution line to ward 1,21 and 22 and providing FHTCs. in Kuruva Panchayath Project Division Malappuram
3 Package - I - Construction of 12 m dia well cum pump house , Rest room, Approach bridge, Raw water Pumping main and road reformation . Project Division Malappuram
4 Package - II - Construction of 28 MLD WTP ,13.5 LL OHSR at Keezhmuri, Supplying and laying Testing of 600 mm DI clear water Pumping main to OHSR at Moochikkal. Project Division Malappuram
5 Package - III - Construction of 28 LL OHSR & 7 LL capacity Sump cum Pump house at Moochikkal, Supplying and laying Testing of 400 mm DIClear water pumping main to OHSR at Kuzhaparambu .Distribution System to Mankada Pt and akkraparamba Pt.(Part) Project Division Malappuram
6 Package - IV - Construction of 13 LL OHSR at Perinthattiri, Supplying and laying Testing of Clear water pumping main and Distribution main . Project Division Malappuram
7 Package -IX - Enhancing the Existing distribution line and Laying distribution line to non covered area in Makkaraparamba Panchayath Project Division Malappuram
8 Package - V -Construction of 22 LL OHSR at Kuzhaparambu, Supplying and laying Testing of Distribution System to Mankada Pt and akkraparamba Pt.(Part) Project Division Malappuram
9 PACKAGE - VI - Construction of 13 LL oHSR at chullikkode , Supplying and Laying of Clear water Gravity main from Moochikkal to Chullikkode and CWGM to Puzhakkattiri Pt Zone II . Project Division Malappuram
10 Package - VIII - - Enhancing the distribution system and Providing FHTCs in in Puzhakkatiri Panchayath. Project Division Malappuram
11 Package - X - Enhancing the Existing distribution line and Laying distribution line to non covered area in Moorkkanad Panchayath. Project Division Malappuram
12 Package - XI - Enhancing the Existing distribution line and Laying distribution line to non covered area in Kootilangadi Panchayath. Project Division Malappuram
13 Package - XII - Electro mechanical works - Supply and erection of Raw water, Clear water pumpsets, booster pumpset, Trannsformer at WTP, wiring of Raw water pump house , power line extension and power connection works Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 In Package I(58%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . Well bottom shuttering,reinforcement and concreting completed. In Package II(24%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing.Retaing wall PCC,reinforcement,shuttering and concreting progressing. In Package III(92%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing.Tarring work progressing. SS ladder work for tank progressing. DI pipe interconnection work progressing. Anchor block work progressing. Lightening arrester installation completed.Floor plastering progressing. Compound wall construction progressing. InPackage IV(90%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. DI pipe connection work progressing Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(82%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement and concreting completed. Hand rail shuttering,reinforcement and concreting progressing. In Package VII(90%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . Tarring work progressing. Package VIII(51%)-pipe supplied - Pipe line work progressing. In Package IX(1%)-Work started.Road cutting work progressing. In Package X-Tender invited. In Package XI(25%)-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. Malappuram Project Dn
24 Jan 2024 In Package I(57%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . Well bottom shuttering,reinforcement and concreting completed. In Package II(24%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing.Retaing wall PCC,reinforcement,shuttering and concreting progressing. In Package III(92%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing.Tarring work progressing. SS ladder work for tank progressing. DI pipe interconnection work progressing. Anchor block work progressing. Lightening arrester installation progressing. Compound wall construction progressing. InPackage IV(90%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(79%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement and concreting completed. Hand rail shuttering,reinforcement and concreting progressing. In Package VII(89%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(42%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI(16%)-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. Malappuram Project Dn
18 Dec 2023 In Package I(50%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(17%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing. In Package III(91%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing. InPackage IV(89%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(70%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement progressing. In Package VII(86%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(40%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. Malappuram Project Dn
10 Nov 2023 In Package I(44%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(10%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. In Package III(89%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed. In Package IV(78%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering and reinforcement progressing. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(59%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting progressing. In Package VII(80%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(27%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-Work awarded. In Package XII-Tender invited. Malappuram Project Dn
16 Oct 2023 In Package I(30%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(6%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. In Package III(81%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. In Package IV(61%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering and reinforcement progressing. OHSR floor slab and beam deshuttering progressing. Retaining wall work(RR) progressing. In Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(45%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch and side wall reinforcement progressing. In Package VII(70%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(16%)-pipe supplied - Pipe lineworkprogressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-Work awarded. In Package XII-Tender invited. Malappuram Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/02/2022
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 21 Jun 2022