Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Feb 2024 |
In Package I(58%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . Well bottom shuttering,reinforcement and concreting completed. In Package II(24%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing.Retaing wall PCC,reinforcement,shuttering and concreting progressing. In Package III(92%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing.Tarring work progressing. SS ladder work for tank progressing. DI pipe interconnection work progressing. Anchor block work progressing. Lightening arrester installation completed.Floor plastering progressing. Compound wall construction progressing. InPackage IV(90%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. DI pipe connection work progressing Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(82%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement and concreting completed. Hand rail shuttering,reinforcement and concreting progressing. In Package VII(90%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . Tarring work progressing. Package VIII(51%)-pipe supplied - Pipe line work progressing. In Package IX(1%)-Work started.Road cutting work progressing. In Package X-Tender invited. In Package XI(25%)-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. |
Malappuram Project Dn |
|
24 Jan 2024 |
In Package I(57%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . Well bottom shuttering,reinforcement and concreting completed. In Package II(24%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing.Retaing wall PCC,reinforcement,shuttering and concreting progressing. In Package III(92%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing.Tarring work progressing. SS ladder work for tank progressing. DI pipe interconnection work progressing. Anchor block work progressing. Lightening arrester installation progressing. Compound wall construction progressing. InPackage IV(90%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(79%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement and concreting completed. Hand rail shuttering,reinforcement and concreting progressing. In Package VII(89%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(42%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI(16%)-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. |
Malappuram Project Dn |
|
18 Dec 2023 |
In Package I(50%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(17%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. 600 mm DI pipe line work progressing. In Package III(91%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed.DI pipe fitting on tank progressing.Tar supplied for road tarring. Floor plastering progressing. Hand rail painting progressing. InPackage IV(89%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering, reinforcement and concreting completed. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(70%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting completed. Roof beam and roof slabI shuttering and reinforcement progressing. In Package VII(86%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(40%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-PVC pipe supplied. 90 mm PVC distributionwork progressing. . In Package XII-Tender invited. |
Malappuram Project Dn |
|
10 Nov 2023 |
In Package I(44%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(10%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. In Package III(89%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. Deshuttering of roof slab and roof beam completed. In Package IV(78%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering,reinforcement and concreting completed. OHSR floor slab and beam deshuttering completed. Retaining wall work(RR) progressing. Plastering work progressing.OHSR roof slab and roof beam shuttering and reinforcement progressing. Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(59%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch reinforcement and concreting completed. Side wall reinforcement,shuttering and concreting progressing. In Package VII(80%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(27%)-pipe supplied - Pipe line work progressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-Work awarded. In Package XII-Tender invited. |
Malappuram Project Dn |
|
16 Oct 2023 |
In Package I(30%)-Supply of Pipes in progress. Pipe line work progressing .Road restoration work -GSB filling work progressing and Tarring work and concreting progressing . Well digging completed . Fixing of dowel bars completed. PCC of steining bottom completed . Reinforcement of steining , Shuttering and Concreting progresses . In Package II(6%)-Soil test Carried out.Site clearing for water treatment plant progressing. DI and pvc pipe supplied. In Package III(81%)-Supply order placed for DI & PVC pipes- pipe supply completed . Pipe line work progressing- Road restoration: GSB filling work under progress . Pressure test on pipe line carried out . Stair reinforcement ,shuttering and concreting of landing completed .Beam for stair- Reinforcement , shuttering and concrete completed. . 3rd brace beam shuttering,reinforcement work and concreting completed . OHSR floor slab shutttering, reinforcement work and concrete completed . Stair out side ohsr tank reinforcement ,shuttering and concreting completed. .Plastering work Progressing.OHSR side wall reinforcement and concreting completed. Haunch reinforcement work, Shuttering work and concreting completed .Masonry work progressing. Side wall reinforcement and concreting completed. Floor beam and slab de shuttering completed. Wall deshuttering completed.Roof slab and roof beam shuttering,reinforcement and concreting completed. Ground floor sunshade shuttering ,reinforcement and concreting completed. Hand rail work progressing. In Package IV(61%)-Pipe laying work progressing. Road restoration-GSB Work progressing . Stair reinforcement , shuttering and concreting progressing. 2nd brace beam shuttering ,reinforcement and concreting completed . Column above 2nd brace beam reinforcement , shuttering and concreting completed . OHSR Floor beam and floor slab reinforcementand concreting completed. Haunch reinforcement and concreting completed. Side wall shuttering and reinforcement progressing. OHSR floor slab and beam deshuttering progressing. Retaining wall work(RR) progressing. In Package V(36%)-Pipe laying work Progressing .Road restoration: GSB filling work progressing . Concrete work progressing.Tank site clearing progressing. In Package VI(45%)-Pipe supply progressing. Pipe line work progressing. GSB filling work progresing.Road concreting progressing. Tank Work- Earth excavation for footings completed. Pcc work completed . Footing reinforcement ,shuttering and concreting completed. column above footing upto plinth level reinforcement ,shuttering and concreting completed . Retaining wall work completed. Earth filing work completed. Plinth beam reinforcement , shuttering and concreting Completed. Stair shuttering, Reinforment and concreting progressing. Brace beam shuttering,reinforcement and concreting completed. Column above brace beam reinforcement work , shuttering and concrete completed. OHSR floor beam and floor slab Shuterring and reinforcement work and concreting completed.OHSR haunch and side wall reinforcement progressing. In Package VII(70%)-Pipe line work progressing .Tarring work progressing .Concrete work progressing .GSB filling work progressing .316 nos of FHTC completed . In Package VIII(16%)-pipe supplied - Pipe lineworkprogressing. In Package IX-Work awarded. In Package X-Tender invited. In Package XI-Work awarded. In Package XII-Tender invited. |
Malappuram Project Dn |
|