Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM Sreenarayanapuram Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening

Project JJM Sreenarayanapuram Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening
Project Code TCRJJM08203817P9
Type Package
Main Project JJM SN Puram Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM Sreenarayanapuram Panchayath PHASE I-CWSS to Nattika Firka-Providing FHTC to Rural households from ongoing scheme (MVS) including Distribution Strengthening
Status On-going
District Thrissur
Executing Office Mathilakam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 136200000
TS Number TS/2021-2022/2021/31507
Technical specification
Contractor M V VISWANATHAN (Mob: 9447079850)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/06/2022
Scheduled date of Completion as per agreement 17 Jun 2023
Expected date of Completion Date is not specified

Processing Dates

TS Date 08 Dec 2021
Estimate Approval 08 Dec 2021
NIT Approval 17 Mar 2022
Tender Closing 08 Apr 2022
Technichal Pre-Qualification 08 Apr 2022
Price bid opening 11 Apr 2022

Approval Dates

Workorder Date 18 Jun 2022
NA 16 Jul 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mathilakam AE
Date: 27/06/2024

Work in progress | 59% Completed

OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing..

Attached images

img

Mathilakam AE
Date: 26/06/2024

Work in progress | 59% Completed

OUT OF 3188 FHTC, 2906 HTC COMPLETED, 50 mm PVC pipe -20934.5/21000m as laid. 14th and part bill submitted.connection work and measurement ongoing..