Project | Jal Jeevan Mission (JJM)-Pindimana Panchayath-Providing FHTC to rural households in Pindimana Panchayath-Phase II-Pipeline Work |
---|---|
Project Code | EKMJJM082015205P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-Pindimana Panchayath-Providing FHTC to rural households in Pindimana Panchayath-Phase II-Pipeline Work |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Pindimana Panchayath-Providing FHTC to rural households in Pindimana Panchayath-Phase II-Pipeline Work |
Status | On-going |
District | Ernakulam |
Executing Office | Kothamangalam Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 20000000 |
TS Number | TS/17601/2023_26_1_1 dated 22/07/2023 Reg No.9782/2023-2024 |
Technical specification | Nil |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 24/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 23 Feb 2024 |
Expected date of Completion | 23/02/2024 |
TS Date | 22 Jul 2023 |
---|---|
Estimate Approval | 22 Jul 2023 |
NIT Approval | 22 Jul 2023 |
Tender Closing | 02 Aug 2023 |
Technichal Pre-Qualification | 04 Aug 2023 |
Price bid opening | 04 Aug 2023 |
Workorder Date | 18 Aug 2023 |
---|---|
NA | 24 Aug 2023 |
Kothamangalam PH Sn 2 - AE |
Date: 25/06/2024 |
Work in progress | 78% Completed
ongoing.
Muvattupuzha PH Dn EE |
Date: 20/04/2024 |
Work in progress | 78% Completed
work in progress.