Project | JJM - Phase 3- Providing FHTC in Perambra Grama Panchayath in Kozhikode District from WSS in Permabra Panchayath |
---|---|
Project Code | CLTJJM022212648P1 |
Type | Package |
Main Project | JJM - Phase 3- Providing FHTC in Perambra Grama Panchayath in Kozhikode District from WSS in Permabra Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - Phase 3- Providing FHTC in Perambra Grama Panchayath in Kozhikode District from WSS in Permabra Panchayath |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 241800000 |
TS Number | TS/2022-2023/2022/9712 |
Technical specification | 1) 3188numbers of FHTCs 2)18 LL GLSR 3)CWPM from Chilambuvalavu to the Proposed GLSR at to Cheramala -1648m 4)Distribution 200mm DI -2575m 250mm DI - 515m 450mm DI - 1545m 90mm PE- 50,000m 110mm PE -15000m 140mm PE - 2000m 160mm PE- 1500m Total =73135m |
Contractor | M/S Novel Constructions (Mob: 9847020004) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 28/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 14 Jul 2023 |
Expected date of Completion | 31/08/2024 |
TS Date | 07 Jul 2022 |
---|---|
Estimate Approval | 07 Jul 2022 |
Tender Closing | 06 Aug 2022 |
Price bid opening | 09 Aug 2022 |
Workorder Date | 15 Oct 2022 |
---|---|
NA | 28 Oct 2022 |
Kozhikode Project Dn AE4 |
Date: 24/06/2024 |
Work in progress | 83% Completed
90mm PE - 49,000m, 110 PE - 4000m, 140mm PE - 1642m, 160mm PE-1471m Supplied. 90mm PE -41526m, 140mm PE - 480m, 110mm PE - 5376m, 160mm PE - 840m laid, total laid = 48222m, Laying work in progress and 18 LL GLSR - Roof - completed, Plastering work in progress. 1214 HTCs provided. work in progress. .
Kozhikode Project Dn AE4 |
Date: 23/06/2024 |
Work in progress | 83% Completed
90mm PE - 49,000m, 110 PE - 4000m, 140mm PE - 1642m, 160mm PE-1471m Supplied. 90mm PE -41526m, 140mm PE - 480m, 110mm PE - 5376m, 160mm PE - 840m laid, total laid = 48222m, Laying work in progress and 18 LL GLSR - Roof - completed, Plastering work in progress. 1214 HTCs provided. work in progress. .