JJM-2020-21- Phase 1 - RWSS to Sooranadu South - Providing pipeline extension, supply and erection of pumpsets in Sooranadu South Grama panchayath

Project JJM-2020-21- Phase 1 - RWSS to Sooranadu South - Providing pipeline extension, supply and erection of pumpsets in Sooranadu South Grama panchayath
Project Code KLMJJM08209100P1
Type Package
Main Project JJM-2020-21- Phase 1 - RWSS to Sooranadu South - Providing pipeline extension, supply and erection of pumpsets in Sooranadu South Grama panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21- Phase 1 - RWSS to Sooranadu South - Providing pipeline extension, supply and erection of pumpsets in Sooranadu South Grama panchayath
Status On-going
District Kollam
Executing Office Sasthamcottah WS Sn1
Agreement Number
Agreement Date
TS Amount (Rs) 17600000
TS Number 12548/2021-2022
Technical specification pipe line extension work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/02/2022
Scheduled date of Completion as per agreement 23 Jun 2022
Expected date of Completion 30/04/2024

Processing Dates

TS Date 07 Nov 2021
Estimate Approval 07 Nov 2021
NIT Approval 11 Nov 2021
Tender Closing 22 Nov 2021
Technichal Pre-Qualification 27 Nov 2021
Price bid opening 27 Nov 2021

Approval Dates

Workorder Date 09 Dec 2021
NA 24 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sasthamcotta WS Sn 1 - AE
Date: 26/06/2024

Work in progress | 77% Completed

Work temporarly stopped, due to the getting delay in RE sanction.Out of 11 km - 10.20 km laying work completed..

Sasthamcotta WS Sn 1 - AE
Date: 25/06/2024

Work in progress | 77% Completed

Work temporarly stopped, due to the getting delay in RE sanction.Out of 11 km - 10.20 km laying work completed..